METHOD STATEMENT FOR RAMP SLAB FORMWORK AT STARTING POINT

Slab-Formwork
Slab-Formwork

Purpose of work: It describes the methodology for the execution work for the Ramp Slab Formwork from Starting Point
EXECUTION

  1. Surveyor has given marking for the proper measurement for the Ramp Level and Length.
  2. The slope started towards maximum 40 cm. ht. from SSL.
  3. After casting the slope area from 0.00 level to 40cm ht., we have to start wood formwork/ shutter towards Water Tank Area.
    With this, we are assuring that the 40 cm. ht. is enough and accessible to do the de-shuttering/ dis- mantling of formwork .
    Note: Kindly see Submittal Ref. No. CC/AP/269/00/126
    Submission of Shop Drawing for Ramp Shuttering at Basement 2 ( Formwork)

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version