Improper procedure for the tile nomination and delivery

Slow Progress

Slow Progress

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E

Sub                  : Improper procedure for the tile nomination and delivery as well as other issue for selection

Dear Sir,

With reference to above we would like to highlight our serious concern for tile supply and nomination, which is creating issue at site, kindly note the following:

  1.  The specific tile supplier is not nominated for our project  and contact  details are not provided for documentation to the Contractor. We received only combined intimation.
  1. We are attaching the colour coding for the tile received, tile ordered and clarification with below indicative colors:

a)Yellow Colour – Tile  reecived

b)Red Colour – Client need to specify supplier and selection with code

c) Green Colour – Additional tile ordered, LPO issued

d) White Colour – Not Contractor scope for ID

So, kindly review our concern and help us to have proper procedure to identify, audit , follow and receive the correct material with proper documentation and invoice .

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager