Date: xxx

Ref no: xxx

To             :M/s xxx Center

Project     : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai

Subject     :Regarding immediate submission of shop drawings and materials to avoid delay in partition work and coordination

Dear Sir,

With reference to the above, we would like to inform you that, we are waiting for the following to be submit and approval by the consultant and client as we required for partition and ceiling coordination work.

  1. The Shop drawing for the doors along with material not yet submitted and no timeline has been given for the mandatory approvals.

            So, we want to intimate you, to provide your shop drawing and confirmation that, our design wall thickness will accommodate your double shutter and frame as per your shop drawing approved by the consultant.

So, kindly note that our shop drawing for the partition and mock up room painting including ceiling drawing are pending .

We need your prompt action and reply inline of our requirement as mentioned above.

Till then our submissions will remain under hold.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager