How to Write a Narrative Report for an Extension of Time (EOT) Claim Submission.

How to Write a Narrative Report for an Extension of Time (EOT) Claim Submission

How to Write a Narrative Report for an Extension of Time (EOT) Claim Submission

Introduction

An Extension of Time (EOT) claim narrative report provides a clear, detailed explanation of the reasons for requesting more time to complete a project. The narrative should be structured logically, outlining the causes of the delay, the impact on the project, and how the delays justify additional time. A well-prepared report includes factual information, supporting documentation, and a concise yet comprehensive explanation to support the claim.

Here is a step-by-step guide on how to write an effective EOT narrative report:

1. Project Overview

Begin with a brief introduction about the project to provide context. Include key details such as:

This section sets the stage for the reader and provides basic information about the project.

2. Executive Summary

This section summarizes the reasons for the EOT request and highlights the key delays and events that caused the request. It is a high-level overview that gives the decision-makers a quick understanding of the claim. The summary should include:

3. Description of Delay Events

Describe in detail the events that caused the delay. For each event, include:

Example:

Delay Event 1 – Change in Design:

4. Impact on the Project Schedule

In this section, explain how each delay event affected the project’s critical path. This is a crucial aspect of justifying an EOT claim, as the critical path activities directly influence the project completion date. If possible, use a Time-Impact Analysis (TIA) to demonstrate how each delay pushed back the project schedule.

Example:

The four-week HVAC redesign delay impacted the critical path as the mechanical, electrical, and plumbing (MEP) installation could not proceed without approval of the revised design. This pushed back the project’s critical activities, including MEP system installation, causing an overall delay to the project’s completion by four weeks.

5. Mitigation Efforts

Explain any steps the contractor took to minimize the impact of the delays. This shows a good-faith effort to mitigate delays and avoid further extensions. Examples of mitigation strategies might include:

Highlighting mitigation efforts shows that the contractor attempted to minimize delays and supports the legitimacy of the EOT request.

6. Supporting Documentation

List and reference any supporting documents that are attached to the narrative report. These could include:

This documentation provides objective evidence to support the EOT claim. Ensure that the documents are well-organized and directly tied to the events described in the narrative.

7. Conclusion

Summarize the key points in the report, reiterating the total requested extension and the reasons for it. You should also express the contractor’s commitment to completing the project successfully and within the newly requested timeframe.

8. Submission Information

Include a section at the end of the narrative with the contractor’s name, project manager’s name, and the date of submission. This ensures that the report is official and serves as a point of reference for future communication.

Sample Outline of an EOT Narrative Report:

Project Overview:

Executive Summary:

ABC Construction Ltd. is submitting this Extension of Time (EOT) claim due to unforeseen events that have impacted the project’s critical path. These events include adverse weather conditions, client-requested changes in design, and delays in material delivery. Collectively, these events have caused a delay of 75 calendar days. As a result, we request an extension of the project completion date to March 15, 2024.

Delay Events:

Event 1: Adverse Weather Conditions

Event 2: Design Changes

Impact on Project Schedule:

Due to the above-mentioned delays, the revised project completion date is now March 15, 2024. The total impact on the schedule is 75 calendar days.

Conclusion:

In light of the delays caused by adverse weather and client-requested changes, ABC Construction requests an Extension of Time of 75 days, moving the project completion date to March 15, 2024.

Submitted By:

ABC Construction Ltd.
[Name]
Project Manager
[Date]

By following this format, your narrative report will provide a comprehensive and well-structured justification for the Extension of Time claim, increasing its chances of approval.