GUEST ROOMS SNAGS

Snagging and De-snagging
Snagging and De-snagging

Our Ref: xxx

Date: xxx

To                    :           xxx Construction Co. L.L.C.

                                    P. O. Box xxx

            Dubai – UAE.

Attention          :           xxx

                        :           Sr. Project Manager

Project             :           xxx Park Hotel Dubai

Subject            :           GUEST ROOMS SNAGS

Dear Mr. Rajesh Kapil,

We received your letter Ref: xxx regarding the snagging of the pods on 3.43PM Thursday 30.05.xxx.

As you know all pods are finished completely in our factory inspected before delivering to site. We are doing the snagging in these levels for so long time. We have send you notification of our pods being damaged at site by others.

However we are ready to cooperative and will send our QC Engineer to do the survey on 1st June xxx and complete the work as required. A short notice of 24 hours when tomorrow is Friday is not acceptable.

Hope you understand and cooperate.    

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.