Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Sub: Your letter reference AP/269/CC/249  Dt:  16-02-2017 for “Dry Partition Walls Variation” and further explanation.

Our  design was submitted by GYPSEMNA based on authority request as per tender drawing  (pg-2), project specification in minimum required dB (pg-5) as well as acoustic study provided (pg-6) by your office (letter reference no. AP/269/CC/114  – pg- 6-8) .

  1. From two pre -qualified companies, one is Gyproc  and other is Gypsemna, we also received the proposal from Gyproc that was designed exactly as per tender drawing and required value of dB and there is margin for tolerance i,e. 7dB (international standard) .

Whereas  Gypsemna proposed their system exactly as per our specifications with reference no. CC/AP/269/MAT/CIV/110 Dt: 17-09-2016 and you commented approved as noted i.e. within the authority requirement and tolerance value ( first approved submission pg no. 51, 52 with field test report carried out by Drywall Technical Consultants (pg-54,55). There is no authority requirement mentioned in any of our approved document( bldg. permit –pg 20 issued without any partition drawing).

The contractor also mentioned (pg no 65-67) “Detail of wall partition from specification/shop drawings proposal- 1 and revision plan”, which is self explanatory between project requirement, previous submission and last submission under heading new submission and changes instructed in last meeting and the new proposal by Gypsemna prepared on 30-11-2016 (pg 68-81)

Consultant commented on 20-11-2016 based on our letter ref CC/AP/179/16 Dt: 14.11.16 on our submittal to retain the toilet wall dB 55 instead of 39 (pg-82-95)

  1. The consultant commented on our submittal CC/AP/217/16 on 02-01-2017 through letter AP/269CC/207 (pg-137-140) where consultant also explained for the partition variation at   P-08A.
  1. Arkiplan forwarded contractor’s letter dt: 29-12-2016 by highlighting contractor letter the issues related to mock up room requirement including contractor intimated about drawing released by ID and incorporating changes in the mock up room shop drawing at partition wall (pg- 141-147)  including document transmittal Dt 28-12-206 ref: AP/269CC/36.
  1. On 15-01-2017 the contractor intimated that the client has approved the final drawings and dB’s on 12-01-2017 (the meeting held at site 08-01-2017 with Mr.Girish of Arkiplan, Mr.John of Citymax, Mr.Ramlal for Chirag and Ms.Aveera from Gyproc. In that  meeting decided that the contractor should submit 55dB for room partition and final drawing was submitted accordingly. The client given the approval to go ahead with 55 dB verbally to start and contractor attached the entire scenario including intimation of the variation).

In the same communication item no. 04 is self explanatory and contractor attached the document related variation and original scope of work after approval of our shop drawing with comment (pg-159) in the documents from pg-148 to 166 ( the same letter is reattached for clarity).

  1. Contractor intimated on 25-01-2017 under the heading “ Regarding our reply of minutes held at citymax office dated 05-01-2017and request for the extension of time till 31-08-2017 and approve the variation” as well as intimation of the further delay and the chronological major event attached (pg 167-169).
  1. On 13-02-2017 contractor re-intimated for partition wall variation for time and cost both by attaching the chronological events in summarized form under the heading ”ACCOUSTIC VALUE AND CONTRACTOR’S DOCUMENT FROM TENDER SPECIFICATION, DM AND ID” from serial no 01-15 (pg 178).

Contractor also attached “DETAILS OF COMMUNICATION IN CHRONOLOGICAL ORDER FOR ALL THE EVENTS FOR GYPSUM PARTITION WORK IN TYPICAL FLOOR” (pg 179-183) in item no. 01 -15 having explanation for the communication form 26-06-2016 to 15-01-2017.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager