Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject                :DELAY ISSUE FOR THE PARTITION WORK AT TYPICAL FLOOR  AND  NOTICE FOR DELAY UNDER CLAUSE 53.1 AND OUR VARIATION CLAIM AS PER CLAUSE 51.1.Your ref : AP/269/CC/245 (In reply of your communication ref     no:AP/269/CC/237 DT.06.02.17)

Dear Sir,

With reference to the above, we would like to inform you that partition work at our above mentioned project is being delayed extremely and issue started Dt.  17-09-2016 and finally drawing approved on Dt 14-01-2017 and the mock up room work is in progress because of other pending issues and nomination of the sub contractor and kindly note the following in reply of your communication  ref no:AP/269/CC/237 DT.06.02.17:

  1. We are attaching the major communication documents arranged in chronological order from pg no 01- 183 along with the summary sheet attached in the last (pg 179-183) is self-explanatory to explain the communication from pg no 01-178 to summarize the scenario and occurrence of the events.

So, we are hereby intimating that our claim for the extension of time for the partition work should be considered from 15.08.16 to 14.01.17 i.e.,152 days and this delay impacted all other successor activities linked with the partition activities at every floor.

Furthermore, the cost variation being assessed due to change in the specification and will be submitted accordingly, the final amount or kindly advise to proceed for the 3rd floor and above and close the issue once for all to avoid any further delay.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager