Meetings held between the consultant and M/s xxx or any instructions directly by the client to change the design of partition for our project

Site Meeting

Date:xxx Ref No. xxx To                    : M/s Gypsemna Kind Attn          :Ms.Abeer Project             :2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha,  Dubai Subject: To provide the meetings held between the consultant and M/s xxx or any instructions directly by the client to change the design of partition for our… Continue reading Meetings held between the consultant and M/s xxx or any instructions directly by the client to change the design of partition for our project

Our confirmation for production of the glass wool material (Audio Insul) for xxx, Dubai

Rockwool panel

Date: xxx TO, The Manager Dubai Central Laboratory Department Dubai. Kind Attn         :  xxx Project             : 2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai Subject             : Our confirmation for production of the glass wool material (Audio Insul) for xxx, Dubai Dear Sir, We are hereby confirming that… Continue reading Our confirmation for production of the glass wool material (Audio Insul) for xxx, Dubai

Our serious concern for approval procedure without any documentation and direct approval from the client

Approval and Finalization

Ref: xxx To                     :  M/s xxx INTERNATIONAL FZE Kind Atten       : Mr. xx Project            :  2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at                            Al   Barsha 1st, Dubai U.A.E. Subject             : Regarding our serious concern for approval procedure without any documentation and direct approval from the… Continue reading Our serious concern for approval procedure without any documentation and direct approval from the client

Your Cheque No. xxx , RAK Bank issued to xxx Contracting against advance payment

Advance-Payment-Bank-Guarantee

Date: xxx Ref: xxx To                 : Total , Dubai, UAE Project          : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject:        Your Cheque No. xxx , RAK Bank issued to xxx Contracting against advance payment Dear Mr. xxx, With respect to above mentioned subject, we are… Continue reading Your Cheque No. xxx , RAK Bank issued to xxx Contracting against advance payment

Order confirmation to transformer shifting and other DEWA scope

Substation room

Date: xxx Ref: xxx To                 : Total , Dubai, UAE Project          : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai Subject: Order confirmation to transformer shifting and other DEWA scope Dear Mr. xxx, With respect to your quotation ref 104118/QTN/CCL/TEM/DG/10022018 send on 01/03/xxx with following scope,… Continue reading Order confirmation to transformer shifting and other DEWA scope

Work Not Completed for hand over and NCR not closed

Date: xxx Ref. xxx To                    : M/s xxx Trading Company Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Sub               : Work Not Completed for hand over and NCR not closed Dear Mr. Rahul & Mr. Mithesh, With reference to the above, we kindly… Continue reading Work Not Completed for hand over and NCR not closed

Submission of current invoice and to claim of material delivery

delivery of Tiles and cheque copy.

Date: xxx Ref. xxx To                    : M/s xxx Trading Company Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Sub                  : Regarding your submission of current invoice and to claim of                                   material delivery Dear Mr. Rahul & Mr. Mithesh,          With reference to… Continue reading Submission of current invoice and to claim of material delivery

Regarding rejection of your shop drawing due to non-inspection

Claim rejected

Date: xxx Ref. xxx To                    : M/s xxx Trading Company Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Sub                  : Regarding rejection of your shop drawing due to non-inspection of                              material Dear Mr. Rahul & Mr. Mithesh, With reference to above we… Continue reading Regarding rejection of your shop drawing due to non-inspection

Not to fix pool tile as we instructed to your foreman before waterproof

concrete-pool-deck

Date: xxx Ref. xxx To                    : M/s xxx Trading Company Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Sub                  : Not to fix pool tile as we instructed to your foreman before water proof Dear Mr. Pravinder We are hereby inform you we… Continue reading Not to fix pool tile as we instructed to your foreman before waterproof

Fix the tank and complete installation in pump room with

Pump Room

Date: xxx Ref. xxx To                    : M/s xxx Trading Company Project             : 2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Sub                  : Regarding to fix the tank and complete installation in pump room with                           pipe line. Dear Mr. Rahul & Mr. Mithesh, With reference… Continue reading Fix the tank and complete installation in pump room with