Termination of HVAC works Subcontract Agreement MCM-P1010-SCA-HVACW-03-2020-R1

Contract Documents

Date    :           31st January xxx Ref.      :           xxx/P1010/PM/2021/03 To        :           M/S. xxx Electromechanical Services LLC Dubai, United Arab EmiratesTel: xxx Email id: xxx@gmail.com Attention:       Mr. xxx – Managing Partner Project :           Proposed Private G+1+R Villa on Plot No: xxx At Al Barsha South First, Dubai-U.A.E. For Mr. xxx Subject:           Termination of HVAC works… Continue reading Termination of HVAC works Subcontract Agreement MCM-P1010-SCA-HVACW-03-2020-R1

Reply – HVAC Work in progress

CVI

Date    :           27th January xxx Ref.      :           xxx/P1010/PM/2021/02 To        :           M/S. xxx Electromechanical Services LLC Dubai, United Arab EmiratesTel: xxx Email id: xxx@gmail.com Attention:       Mr. xxx – Managing Partner Project :           Proposed Private G+1+R Villa on Plot No: xxx At Al Barsha South First, Dubai-U.A.E. For Mr. xxx Reference:      xxx letter xxx/P1010/PM/2021/01… Continue reading Reply – HVAC Work in progress

Final notice to correct HVAC Works

shake-up-sales-meeting

Date    :           19th January xxx Ref.      :           xxx/P1010/PM/2021/01 To        :           M/S. xxx Electromechanical Services LLC Dubai, United Arab EmiratesTel: xxx Email id: xxx@gmail.com Attention:       Mr. xxx – Managing Partner Project :           Proposed Private G+1+R Villa on Plot No: xxx At Al Barsha South First, Dubai-U.A.E. For Mr. xxx Subject:           Final notice to correct… Continue reading Final notice to correct HVAC Works

Temporary Occupation permit/NOC for adjacent plot xxx.

No objection letter

Date: 6th February xxx M/s. Dubai Municipality Dubai – U.A.E Phone : 800900   Attention        :           Engr. xxx Projects          :           Proposed Private G+1+R Villa on Plot No: xxx at Al Barsha South First, Dubai-U.A.E. For Mr. xxx Our Ref.         :           xxx/P1010/DM-002/2021   Subject           :           Temporary Occupation permit/NOC for adjacent… Continue reading Temporary Occupation permit/NOC for adjacent plot xxx.

Removal of Tree

Tree Removal

REF: No. xxx/1013/DOC/2021/01 Date: xxx Project: G+1+R Villa + Service Block, Plot No. xxx, at Jumeirah Second, Dubai, UAE. Client: Mr. xxx Subject: Removal of Tree Dear Sir, With reference to the above mentioned subject, on behalf of Mr. xxx, the owner of the Plot No. xxx, we would like to bring to your notice… Continue reading Removal of Tree

Project Commencement date

Keys Handing over

Date    :           xxx Ref.     :           xxx/1013/ALAB/2021/001 To       :           xxx Architects & Engineers,                                                                 PO Box No -xxx Phone: 04 xxx Dubai, UAE Attention:       Engr. xxx Project:          G+1+R Villa + Service Block, Plot No. xxx, at Jumeirah Second, Dubai, UAE. Client:            Mr. Anwar Abuulla Mustafa Subject:          Project Commencement date Dear Sir,… Continue reading Project Commencement date

Introduction of Engr. xxx – Senior Project Engr 

CVI

Ref:       xxx/1015/A&B/2021/01 Date:     xxx To:         xxx Consulting  Architects  &  Engineers                                                              PO Box No.: xxx Dubai, UAE Phone: xxx                                                                           Project: Construction of Villa on Plot No. xxx at Jumeirah 2 Dubai for Mr. xxx Subject: Engr. xxx – Senior Project Engr  Dear Sir, With reference to the above-mentioned subject, xxx appointed… Continue reading Introduction of Engr. xxx – Senior Project Engr 

Certification of Gate Level Marking

surveyor work

REF: No. xxx/1014/AA/2021/05 Date: xxx xxx ARCHITECTURAL & ENGINEERING CONSULTANCYOffice No. xxx, Sobha Ivory 2, Business Bay P.O. Box xxx, Dubai, UAE Project: Residential Villa (G+1) & Pump Room Block, On Plot No. xxxat Al Barari – Dubai, UAE for Mr. xxx Subject: Certification of Gate Level Marking Dear Sir, With reference to the aforementioned… Continue reading Certification of Gate Level Marking

Confirmation on non-requirement of Mobilization NOC from DDA

shake-up-sales-meeting

Ref. xxx/1014/AA/2021/04 Date: xxx xxx ARCHITECTURAL & ENGINEERING CONSULTANCYOffice No. xxx, Sobha Ivory 2, Business Bay P.O. Box xxx, Dubai, UAE Project: Residential Villa (G+1) & Pump Room Block, On Plot No. xxxat Al Barari – Dubai, UAE. Client:  Mr. xxx Subject: Confirmation on non-requirement of Mobilization NOC from DDA Dear Sir, With reference to… Continue reading Confirmation on non-requirement of Mobilization NOC from DDA

Project Team member’s introduction

Justification for Manpower in Month of April xxx

REF: No. xxx/1014/AA/2021/03 Date: xxx xxx ARCHITECTURAL & ENGINEERING CONSULTANCYOffice No. xxx, Sobha Ivory 2, Business Bay P.O. Box xxx, Dubai, UAE Project: Residential Villa (G+1) & Pump Room Block, On Plot No. xxx at Al Barari – Dubai, UAE for Mr. xxx Subject: Project Team member’s introduction Dear Sir, With reference to the above… Continue reading Project Team member’s introduction