Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in tower crane

Reply - Notice of Delay
Reply - Notice of Delay

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Intimation for the Work under hold between 11th to 12th floor vertical element due to over night rain , wind and electrical fault in tower crane

Dear Sir,

With reference to above, there was over night rain from thursday night to Saturday (16.02.17 -18.02.17) and there was a heavy wind and because of that we could not work yesterday (18.02.17) at floor no.11 for vertical element and note the following:

  1. Due to over night and morning rain, the tower crane affected due to moisture and we could not operate for entire day.
  • Because of the heavy wind we could not work for any vertical elements due to non functionability of the crane and wind pressure.

So, this is for your kind intimation that interruption for the progress of slab work from 11th to 12th floor.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version