Work order for paint

Work order for paint
Work order for paint

URGENT

Date: xxx

CC/CI/02

Kind Attn:   The Manager, xxx Interior Division          

Project:       2B + G + 14 + Lower Roof Hotel Building

Plot No.       373-1297 at Barsha, Dubai

Subject:       Work order for paint

Dear Mr. xxx,

With ref. to above we are here

  1. Scope of work:
  2. Surface grinding
  3. Surface preparation by filling material
  4. Painting preparation as per approved  paint system
  5. Quantity re measurable and to be reconfirmed with Mr.Abu Zaed
  • Cost :

                    As per company policy the cost of the material + Cost of labour +  Overhead profit to be added as per company profile will be decided by Finance department.

  • Inspection to be raised at all levels/ stages
  • Quality:

Surface preparation to be prepared as per consultant expectation and approved method of statement. Need to inspection after preparation.

  • Final coat should not be applied, it should be applied at later stage when mentioned.
  • Material and Sample board:
  • Approved material ECP-04 for Basement wall and Ceiling 0852 SIGM ACRYLIC PRIMER SEALER – WHITE , 0815 SIGMA TEXTURE MP (Spotter) –WHITE, 0842 SIGMACRYL FLAT (x2) -0250 for wall and 0842 SIGMACRYL FLAT (x2) – 0350 for Ceiling to be used as per method of statement.
  • Sample board is available at site office for physical examination for texture, please confirm.
  • Safety – safety training and  instruction need to follow as per local rules and regulations

Regards,

For xxx Contracting L.L.C

xxx

General Manager  

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version