Undertaking letter by Main contractor for structural safety /building safety as required in application no: xxx.

Beam Jacketing
Beam Jacketing

Date: xxx

Ref no: CC/DT/DM/09

To,

Dubai Municipality

Building permit section

Dubai, UAE

Project       :    2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-xxx at Barsha, Dubai

Sub      :  Undertaking letter by Main contractor for structural safety /building    safety as  required in application no:241570-23-1.

Dear Sir,

With reference to the above, we the main contractor M/s Chirag contracting  LLC , PO Box:31537, Tel: 04-8867788,  are confirming and undertaking the full responsibility for the safety of the building with existing changes as first floor slab beams wherever the jacketing required.

Furthermore, we are undertaking the responsibility of the entire building safety because of these modifications in the structure at first floor slab area. We also assure to follow the approved drawing, method statement and material for the jacketing.

So, this undertaking is issued as per your comments mentioned in our application no.241570-23-1

Regards,
For xxx Contracting L.L.C

xxx

General Manager  

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.