Unavailability of Free Issue Material.

Reply - Notice of Delay
Reply - Notice of Delay

Our Ref: xxx

Date: xxx

To                           : xxx Contracting Company LLC

                               P. O. Box xxx, Dubai, U.A.E.

Attention            : Mr. xxx, Senior Project Manager

Project                 : xxx Tower, Dubai – U.A.E.

Subject                 : Unavailability of Free Issue Material.

Dear Sir,

I’m writing to inform you that we have ran out of Wash Basin (Roca – xxx)  on 25 April xxxx as I informed in my email attached (appendix 1)

The unavailability of this Free Issue Material is preventing from completing and signing off pods starting today 27 April xxxx and will therefore impact the production and delivery schedule.

We remind you again that the ongoing lack of available Free Issue Materials required for Pods type 2 (accessible pods) is also preventing us from completing these pods as per the production plan.

We urge you to share the dates of arrival of all the pending Free Issue Materials to plan the production accordingly.

Yours faithfully,

On behalf of M/s xxx (Contractor Name) LLC

xxx

Projects Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version