Date                : xxx

Ref                   : xxx

To                    : M/S xxx xxx Hospitality

Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E

Subject          : Regarding our continuous follow up for the nomination issued by the client for Electronic door lock and our concerned

Dear Sir,

With ref. to above, we are showing our total disappointment for the coordination with your company and our continuous follow up have no outcome till date from your end.

Furthermore your personal visit last week on dated 20.11.2017 we again handed over our confirmation for the LPO issue by client and our endorsement of work order, but we didn’t received any feedback from your end.

So, this is our final reminder that we need your reply within 24 hours.

Regards,

For xxx Contracting L.L.C

xxx

General Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version