Surface preparation of  water proofing

Bituminous-Membrane-Waterproofing
Bituminous-Membrane-Waterproofing

Date: xxx

Ref. xxx

To:

M/s. xxx Consulting Architects and Engineers

Dubai, UAE

Kind Attn:     Mr. xxx

Project:          2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai.

Subject:             Surface preparation of  water proofing

Dear Sir,

               As per site visit on today evening Mr.xxx said that the surface is not ready to receive primer at water tank area at basement –II level.

   Here as a contractor this area is our responsibility to precede the work which is holding since two days, so the project progress is not suffer as show far.

Regards,

For xxx Contracting L.L.C

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.