Submission of the proposal to close the distribution pump opening in PT slab

Shop Drawing
Shop Drawing

Date: xxx

Ref no: xxx

To

The Manager,

DM Qualification Section (License)

Dubai Municipality,

Dubai UAE

Sub                : Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor

Dear Sir,

With reference to the above, we are hereby submitting the proposal and approval by the consultant and design confirmation by the PT subcontractor and attaching herewith the following for your reference and review.

  1. Consultant approval
  2. Method of statement
  3. VLM Emirates (PT subcontractor design confirmation
  4. DM approved drawing for temporary opening
  5. Design proposal for closeout with “L” angle and rebar

So, kindly review and request to close the violation

Thanks with Regards,

xxx

(Managing Director)

xxx Contracting L.L.C

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version