Submission of Test Certificate of lifting Hook from third party.

Load Test Hook Inspection
Load Test Hook Inspection

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject      :Regarding to submission of Test Certificate of lifting Hook from third party.

Dear Sir,

As per the lift contractor requirement and our letter reference no on dated xxx, xxx, the work has been carried out as we intimated to avoid the delay.

So find the test certificate which are satisfactory and we are submitting our variation claim separately.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan