Submission of Missing Details for Waterproofing in our Previous Submittal

Bituminous-Membrane-Waterproofing
Bituminous-Membrane-Waterproofing

Date: xxx

Ref. xxx

To:

M/s. xxx Consulting Architects and Engineers

Dubai, UAE

Kind Attn:     Mr. xxx

Project:          2B + G + 14+ Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai.

Subject:             Submission of Missing Details for Waterproofing in our Previous Submittal CC/AP/269/07/27B  Dt :xx

Dear Sir,

            With reference to the above mentioned subject, in our previous submittal there are some information remain silent or kept blank , kindly find here with the missing information in our comparative statement submitted by Henkel  letter # HPIL/TCS/15327/2015, please note the following

S.noPropertiesFlexobitBituplus EX 4180As per site Specification 2 layer applicationRemarks
Item  # 03Thickness (mm)5.0+0.34In specification 5mmContractor proposal 4 + 4= 8mm
Item # 05Water tightness to liquid water (kpa)3005 bar @ 50m The Bituplus EX 4180 excellent resistance to positive water & vapor Pressure
Item # 06Elongation at break length direction100040/50 Flexobit is 1000%  because of  non –reinforcement homogeneous pure bitumen but Bituplus EX 4180 40% because of  mixture of bitumen and SBS polymer as well it have stable reinforcement core of non woven spun bond ployster rot-proof fabric
S.NoPropertiesFlexobitBituplus EX 4180As per site Specification 2 layer applicationRemarks
Item  # 09Flow Resistance at elevated temperature90No flow till 100 degree centigrade  
Item # 12Reaction to FireFFl Both the materials by product of the petrol chemical (No fire resistance)

So kindly find the missing information for your kind comparison and further explanation & enabling to comparison to avoid any comments for because of missing item

Regards,

For xxx Contracting L.L.C

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment