Revised the variation for the modification work of the lift entrance door and extra cost

Notification of Variation

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject        : Regarding to revised the variation for the modification work of the lift entrance door and extra cost involve (BOQ rate for concrete, plaster and shuttering should not be applied)

Dear Sir,

With reference to above, we are hereby inform you that we submitted our variation to modify the lift entrance door area with the BOQ rate as it was adopted the standard practice

Now, we completed the modification and it involve heavy cost due to narrow area modification and small quantity of concrete and congested location for shuttering and plaster as well as it took more time also

So, we are hereby requesting we need extra cost for small area modification and BOQ rate not covering our cost even  50% even for concrete, plaster and shuttering and time taken to modification is three times than normal work

This is for your kind information to increase the cost for shuttering, concrete and plaster 100 % more than BOQ, please time accordingly

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version