Request to pay directly to the supplier for long lead item or major procurement items.

subcontractor contract agreement.
subcontractor contract agreement.

Date:               xxx

Ref:                  CC/269/CM/19

To                     : M/s. xxx, Dubai, UAE

Kind Attn          : Mr. xxx

Project             : 2B + G + 14 + Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E.

Subject             : Request to pay directly to the supplier for long lead item or major procurement items.

Dear Sir,

With regards to the subject above, as we discussed with you to help us financially to release the payment for the major item to procure at this stage which help the contractor early delivery.

We are attaching the supplier quotation herewith and find the details below:

Sl No.Description of the item to be procuredName of the supplier and quotation referenceAmount (AED)
1LV SwitchgearSAFETY ELECTRICAL  GROUP Proforma Invoice No: SESM/PI/17/1018 date 11.04.17 P.O No: 1700152728,000.00
2Firefighting pump setBahri & Mazroei Technical Syatem Co. LLC Proforma Invoice No. PI/FFS/SH/17-24-A date 12.04.17241,709.40
3Electric Busbar DuctTransbar Middle East LLC Proforma Invoice No. 1700078  date 11.02.17275,000.00
4GRP Water TanksFikree Pipe LLC Proforma Invoice No. PF0080/17  date 13.04.17133,600.00
TOTAL AMOUNT (AE Dirhams):1,378,309.40

In word AE Dirhams: 1,378,309.00 (AE Dirhams: One million three hundred seventy eight thousand three hundred nine and forty Fils only)

So, kindly do the needful and awaited for your early reply.

Regards,

For xxx Contratcing LLC

xxx

Project Manager

By Md Abu Zaed Khan