Regarding shifting the tower crane support from 3rd floor to 11th floor

Tower Crane
Tower Crane

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Regarding shifting the tower crane support from 3rd floor to 11th floor

Dear Sir,

With reference to the above, we are intimating that, we must shift the tower crane support from 3rd floor to 11th floor now ,which is required to be fixed for the further extension.

We are submitting the confirmation from the tower crane supplier for your information and record and shifting the support.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.