Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals

Elevator Installation work

Elevator Installation work

Date:               xxx

Ref:                 CC/269/LW/13

To:                   Schindler Lift Pars Intl. Ltd

Kind Attn:      Mayur Hingorani

Project:           2B + G + 14 + Lower Roof Hotel Building

Plot No.:          373-1297 at Barsha, Dubai

Subject:          Regarding reconfirmation of delivery time and execution time due to delay in the approval of submittals

Dear Mayur,

With ref. to above, we would like to inform you that process of approvals of the drawings and material submittals are still going on where as the payment has been done long back and kindly provide us the following:

  1. What is the delivery date of the lift after taking the approval from the site?

So, kindly provide us the final drawings with submittal sheet and other required information as mentioned in the above points, the mail conversation is not considered as submittal.

Regards,

For xxx Contracting L.L.C

xxx

General Manager