False ceiling work

False ceiling work

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject    : Regarding Nomination –Public area Fit out works (M/s xxx Group and

                    M/s xxx Interior’s)

Dear Sir,

With reference to the above and your Letter Ref: AP/269/298 dated 09.04.2017 and

Ref: AP/269/299 dated 10.04.2017, and documents received with the same from

M/s Destec Group and M/s Makstylo Interior’s, we would like to highlight the following:

  1. You intimated as per Item No. 1 of your letter, that Main Contratcor to reconfirm the quantities. Main Contractor is not responsible for the discrepancy in quantities in a Lump sum Contract.
  2. We could not find the quotation to determine payment terms and conditions, other inclusions and exclusions etc. which is required to issue the LPO.
  3. In the attached BOQ, Item Wall Finishes, the plastering works has been completed by the Main Contractor and have been included again by the subcontractor. Please note that this scope is covered by the Main Contractor and is not required at the project.
  4. Subcontractor has considered all the doors are fire rated for 30 mins, we provided details as intimated by our letter CC/AP/242/16 dated 21.01.2017 to be confirmed by the consultant for authority approval.
  5. Only the supply of Vanity Counters has been considered by the subcontractor, who will carry out the installation?
  6. Type of Waterproofing at the planter box to be specified.
  7. MEP works and lighting at the reception, pool bar fit out area, wooden areas as well as final touch up after fixing of lunimaries if required to be carried out by the subcontractor.

Regards,