Pods Delivery Schedule for Towers 1, 2 & 3

uploading bathroom Pod

uploading bathroom Pod

Our Ref: xxx

Date: xxx

To                    :           xxx Contracting Middle East,

                                   P.O.Box xxx,

                                   Dubai, UAE 

Attention          :           Ms. xxx

                        :           Project Director

Project             :           xxx Tower Views, Dubai

Subject                 : Pods Delivery Schedule for Towers 1, 2 & 3.

Dear Mr. Chen,

We refer to your letter Ref: xxx dated xxx subjected Pods Delivery Schedule for Tower 1, 2 & 3.

  1. At the outset, we would like to clarify and correct the information and target dates for Towers 2 & 3 mentioned in your letter.
  2. You are referring to a schedule sent from your side on 29th Aug xxx which was not accepted by Xxx, and is not realistically achievable.
  3. We have sent you the procurement and material lead time many times, and explained what is doable and what is not.  Please refer to our letters Ref: xxx dated 29th Jul-19, Ref: xxx dated 21st Aug-19, and all previous emails and letters explaining about the material lead time.
  4. We do not see any benefit, at this stage, in referring to an obsolete schedule that no one on earth can achieve, and that was rejected by Xxx (how can we deliver pods on 21st Sep-19, as you are mentioning in your letter, when we got the contract on 4th of Oct xxx).

Our team shall liaise with you for the inspection and delivery of the 330 pods mentioned in your letter during the coming couple of days.

On behalf of xxx LLC

xxx

Project Manager       