Site icon The Engineers Blog

Regarding pending issue with emirates kitchen and our serious concern for delay of work at site

Kitchen Equipment

Kitchen Equipment

Date: xxx

Ref: CC/EMK/09

To                 : M/s. xxx Kitchen Equipment Company LLC.

Project          : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai

Subject        : Regarding pending issue with emirates kitchen and our serious concern for delay of work at site

Dear Mr. xxx,

With reference to above that has been intimated through our previous mail and find here with the formal intimation that your cooperation and coordination have the issue at site and impact on project progress and your kind attention for the following:

  1. After kitchen nomination there are so many changes in your kitchen drawing because of that we confused which is your final drawing,  so provide us one final drawing by incorporate all changes till date with hard copies has been issued to you did not return back our scanned copy with softy copy
  2.  Regarding the issue of the bear supply line from beverage room to stag bar counter, you must submit the drawing for approved by our consultant. Since we followed one time verbal instruction through our client and you put now new requirement to our MEP sub-contractor as per project protocol you must submit the drawing to main contractor that must be approved by ARKIPLAN as per project protocol.

So submit the drawing with your proper requirement layout and define the scope who will execute the same at site with approved drawing  

So, in short your coordination with us not up to the required level and you are not following the project protocol to submit the drawing to main contractor as well as other issue mentioned above have impact on our project progress.  

Thanks and Regards

xxx

Project Manager