Payment Application No. 18

Delay in the certification of our invoice
Delay in the certification of our invoice

xxx CONTRACTING CO. LLC                                        

P.O Box xxx Dubai, UAE

Tel: xxx

Fax: xxx

Attention                    :   Engr. xxx

                            Project Manager                            

Project                        :  xxx Residential Development

Client             :  M/s. xxx LLC

Consultant    :  M/s xxx and Alami (Consolidate Engineering Co.)

Subject             :  Payment Application No. 18

Dear Sir,

We refer to the Completion Certificate received from Al xxx Contracting Co. LLC reference xxx dated 27th August xxx for the above referred project; we are submitting herewith our Payment Application No. 18 which includes the release of 5% retention in accordance with the contract.

We trust that the attached documents are sufficient for our substantiation, should you need additional information, please do not hesitate to contact us.

We look forward to receive our due payment at the earliest.

Kind Regards,

For xxx Interiors LLC

xxx

Project Manager                                                                                    

By Md Abu Zaed Khan