Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Notice of Delay in the release of the retention (1st part) Dear Sir, We refer to M/s xxx (Contractor Name) letter xxx… Continue reading Notice of Delay in the release of the retention (1st part)
Rejection to the allegations of incomplete insulation works
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Rejection to the allegations of incomplete insulation works Dear Sir, We fundamentally object to the content of your letter reference xxx dated… Continue reading Rejection to the allegations of incomplete insulation works
Notice of Delay in the release of the retention (1st part)
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Notice of Delay in the release of the retention (1st part) Dear Sir, In accordance with our Subcontract agreement ref: xxx, Appendix… Continue reading Notice of Delay in the release of the retention (1st part)
Response to Claim rejection for the incurred transportation cost increase due to the KSA customs regulations
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Response to Claim rejection for the incurred transportation cost increase due to the KSA customs regulations … Continue reading Response to Claim rejection for the incurred transportation cost increase due to the KSA customs regulations
Compiled claim of incurred transportation cost increase resulting from the exceptional
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Compiled claim of incurred transportation cost increase resulting from the exceptional KSA customs regulations following the COVID-19 Pandemic References: Dear Sir,… Continue reading Compiled claim of incurred transportation cost increase resulting from the exceptional
Revised Claim of incurred transportation cost increase due to the KSA customs regulations.
customs regulations. Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Revised Claim of incurred transportation cost increase due to the KSA customs regulations. References: Dear Sir, Following… Continue reading Revised Claim of incurred transportation cost increase due to the KSA customs regulations.
Completion of Type A supply & delivery of Pods
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Completion of Type A supply & delivery of Pods Dear Sir, We are writing to inform you that today we have completed… Continue reading Completion of Type A supply & delivery of Pods
Claim No.3 of incurred transportation cost increase due to the KSA customs regulations
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Claim No.3 of incurred transportation cost increase due to the KSA customs regulations Dear Sir, As previously communicated in our Email dated… Continue reading Claim No.3 of incurred transportation cost increase due to the KSA customs regulations
Claim of incurred cost increase due to the KSA customs regulations
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Claim of incurred cost increase due to the KSA customs regulations Dear Sir, As previously communicated in our Email dated 16th April… Continue reading Claim of incurred cost increase due to the KSA customs regulations
Sea Freight Cost – An alternative solution for delivery
Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention : Mr. xxx, Group Procurement Manager Project : Design and Build of Coastal Village Residential Building. Subject : Sea Freight Cost – An alternative solution for delivery. Dear Sir, As per your request, we have explored the possibility of sea… Continue reading Sea Freight Cost – An alternative solution for delivery