Notice of Claim – Wood Bench at Locker Rooms

Variation notification
Variation notification

M/s xxx Building Contracting LLC       

PO Box xxx, Dubai, U.A.E

T: xxx | F: xxx

Email: xxx

Attention        :   MR. xxx

    Project Manager

 Project         :   xxx Sky Tower – Umm Ramool

Subject:            Notice of ClaimWood Bench at Locker Rooms

Dear Sir,

We refer to the email received from DECC dated 22nd May xxx (copy attached), regarding the Wood Bench at Locker Rooms, please be informed that the aforementioned Bench is not part of our Subcontract Scope of Works, hence, this will be treated as a variation to our contract.

This letter will serve as our official Notice of Claim for this variation, all the relevant cost will be submitted once the requested samples and other requested documents have been approved.

This is for your information, record and necessary action.

Sincerely Yours,

For Xxx (Name of the Subcontractor) Interiors LLC

xxx

Commercial Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.