Narrative report for Window Analysis delay Analysis.

Narrative report for Window Analysis delay Analysis.

Narrative report for Window Analysis delay Analysis.

Project Overview

Introduction

This report provides a detailed Window Analysis Delay Analysis for the ABC Tower Construction Project. The objective of this analysis is to evaluate the impact of delays by focusing on specific time windows within the project schedule. The Window Analysis method helps in identifying how delays within these periods have affected the overall project timeline and determining the necessary adjustments to address these delays.

Window Analysis involves examining distinct time periods (or windows) within the project to assess delays and their impact on the project’s critical path and completion date.

1. Methodology

A. Data Collection

B. Analysis Approach

C. Tools Utilized

2. Analysis of Time Windows

A. Window 1: January 1, 2024 – April 30, 2024

Planned Activities
  1. Site Preparation and Mobilization
  2. Foundation Work
  3. Underground Utilities Installation
Actual Performance
Impact

The delays in foundation work and underground utilities installation caused a shift in the start of subsequent critical activities. This resulted in a cascading effect on the project schedule.

B. Window 2: May 1, 2024 – August 31, 2024

Planned Activities
  1. Structural Steel Erection
  2. Façade Installation
  3. MEP Rough-in
Actual Performance
Impact

The delays in structural steel erection and subsequent façade installation affected the start of the MEP rough-in activities. This period experienced a cumulative delay of approximately 14 days in critical activities.

C. Window 3: September 1, 2024 – December 31, 2024

Planned Activities
  1. Interior Finishing
  2. Final Inspections
  3. Commissioning and Handover
Actual Performance
Impact

Delays in interior finishing impacted the schedule for final inspections and commissioning, resulting in a shift of the completion date by approximately 20 days.

3. Total Impact Analysis

A. Cumulative Delay Assessment

Total cumulative delay observed: 25 days + 48 days + 60 days = 133 days

B. Revised Project Completion Date

The original contract completion date of December 31, 2024, is now projected to be May 14, 2025, based on the cumulative delays across all identified time windows.

4. Causes of Delays

A. Unforeseen Site Conditions

Unexpected underground utilities and unsuitable soil conditions during the initial window caused delays in foundation work.

B. Adverse Weather Conditions

Severe weather during the second window affected structural and façade work, resulting in delays.

C. Design Changes

Design modifications during the second window led to rework and extended time for MEP rough-in activities.

D. Subcontractor Performance Issues

Delays from subcontractors, particularly in the interior finishing and inspection phases, contributed to the extended project timeline.

E. Material Delivery Delays

Late delivery of critical materials affected the façade installation and commissioning phases.

5. Mitigation and Recovery Actions

A. Acceleration of Critical Path Activities

Additional resources and labor are being applied to critical path activities to recover lost time.

B. Improved Coordination with Subcontractors

Enhanced performance management and coordination with subcontractors to ensure timely completion of remaining work.

C. Expedited Material Procurement

Fast-tracking procurement processes for delayed materials to prevent further impact on the schedule.

D. Enhanced Project Controls

Strengthening project controls, including better delay tracking and real-time adjustments to the schedule.

6. Recommendations

A. Regular Schedule Updates

Frequent updates and monitoring of the revised schedule to reflect the current status and adjust for new delays.

B. Extension of Time (EOT) Claim Submission

Prepare and submit an EOT claim to address the cumulative delays and adjust the contract completion date accordingly.

C. Strengthen Project Management

Implement stronger project management practices and controls to better handle future delays and ensure timely completion.

7. Conclusion

The Window Analysis Delay Analysis for the ABC Tower Construction Project reveals significant delays in each of the selected time windows, resulting in a total cumulative delay of 133 days. The revised project completion date is now extended to May 14, 2025.

The project team is actively engaged in implementing mitigation strategies to address delays and prevent further impacts. Ongoing monitoring and adjustments to the project schedule will be essential to achieving successful project completion.

Submitted by:
XYZ Construction Ltd.
[Your Name]
Project Manager
[Date]