Modification for Drainage Pipes in Towers

METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET

To                    :           XXX International Company

            P. O. Box XXX

            Riyadh XX

            KSA.

            Tel: XX

Attention          :           Eng. XXX

                                    Email : XXX

Project             :           XXX Towers, Makkah

Subject            :           Modification for Drainage Pipes in Towers 9, 10 & 11

Dear Eng. xxx,

Based on the telephonic conversation with Mr.xxx and Mr. xxx, we would like to inform you that the attached letter is not a valid response on our requirement. However based on the email confirmation (Please refer to the attached) the changes will not be applicable in the pods on the towers 9, 10 & 11. We will follow the same drainage options in 9, 10 & 11 as the other towers (6, 7, 8, 12, 13 & 14).

This is for your information and our record.

Yours faithfully,

On behalf of xxx LLC

xxx

By Md Abu Zaed Khan