Mock up room cladding under hold due to home automation requirement

awaiting-response
awaiting-response

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Mock up room cladding under hold due to home automation requirement and nomination awaited from the client (new verbal instruction by client)

Dear Sir,

With reference to above, we have completed the framing and cladding partially for mock up room and the balance cladding under hold due to new requirement indicated by the employer during their site visit on dated 22.01.17 for home automation provision.

So, we are waiting the nomination documents from your office for home automation which will be provided by the client as per their verbal instruction.

So, this is the advance information delivery by the client for home automation and balance cladding will be completed after providing the requirement for home automation only.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version