Site icon The Engineers Blog

METHOD STATEMENT UNDER GROUND FIRE FIGHTING WORK

3-tips-for-Fire-Pump

3-tips-for-Fire-Pump

Contents:

  1. Objective
  2.  Scope
  3. References
  4. Material
  5. Material Procurement, Handling and Storage
  6. Trenching & Bedding
  7. Backfilling
  8. Assembly & Laying
  9. BUTT WELD PROCESS
  10. Pressure Testing Outside The Trench
  11. Testing In The Trench
  1. Objective

This method statement provides information concerning the method of construction to ensure compliance with contract requirements, drawing, technical specification and quality control to provide a successful installation, testing, and commissioning of the Installation of U/G HDPE Pipes.

HAC shall complete installation of HDPE pipes including excavation and backfilling, testing, witness testing at the site by the engineer, testing and commissioning of the underground fire fighting work.




PIPE WALL THICKNESS (mm)LIP HEIGHT(mm)HEATING TIME(sec)CHANGING TIME(sec)LINKING TIME(sec)LINKING TIME(sec)
…………4,50,545556
4,5………71,045………705……….65……….66…………10
7………..121,570…….1206……….86……….810……..16
12……….192,0120……1908……….108……….1116……..24
19………262,5190……26010……..1211……..1424………32
26………373,0260……37012……..1614………1932………45
37………503,5370……50016……..2019………2545………60
50………704,0500……70020……..2525………3560………80

  Table: Base values under 20o ambient temperature 

  1. Pressure Testing Outside The Trench
  2. If specified by the engineer, pressure testing may be conducted prior to pipe installation.
  3.  After the pipe has been joined, fill it with water; carefully bleed off any trapped air.
  4. Subject the pipe to a hydrostatic test pressure that is 1.5 times the system design pressure for a maximum of 3 hours. During this time, add water periodically to maintain the test pressure; this compensates for the initial stretching of the pipe. The line pressure tightness is determined by visual observation; therefore, it is not necessary to measure the make-up water.
  5. Examine every joint; any leakage must be repaired and then retested.
  1. Testing In The Trench:
  2. Fill the pipeline with water after it has been laid; bleed off any trapped air.
  3. Subject the lowest element in the system to a test pressure that is 1.5 times the design pressure, and check for any leakage.
  4. The test procedures consist of two steps; the initial expansion and the test phase. When test pressure is applied to a water filled pipe, the pipe expands. During the initial expansion of the pipe under test, sufficient make-up water must be added to the system at hourly intervals for 3 hours to maintain the test pressure. After about 4 hours, initial expansion should be complete and the actual test can start.
  5. When the test is to begin, the pipe is full of water and is subjected to a constant test pressure of 1.5 times the system design pressure. The test phase should not exceed 3 hours, after which time any water deficiency must be replaced and measured. Add and measure the amount of make-up water required to return to the test pressure and compare this to the maximum allowance in the table below.
  6. An alternate leakage test consists of maintaining the test pressure (described above) over a period of 4 hours and then dropping the pressure by 10 psi (0.69 MPa). If the pressure then remains within 5% of the target value for 1 hour, this indicates there is no leakage in the system.
Allowance for expansion under test pressure
Nominal Pipe Size (in)U.S Gal. per 100 ft of Pipe
1 Hours2 Hours3 Hours
6”0.30.60.9
8”0.51.01.5
Exit mobile version