Method Statement Title: Installation of Low Voltage Panels (LVP’s).

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

1.0       Scope

  1. This method statement details the method of installation of L.V main Panels (LVPs) according to the Specification Section 16402.

Note : A separate Method Statement ref. ETA/MS/E-29 shall be submitted for Testing & Commissioning.

2.0       Material

  • All materials shall be as per approved material submittals, shop drawing and single line diagram.
    • L.V. Main Panels.
    • Cable glands and lugs.
    • Identification labels and tags.

3.0       Applicable Location

  • L.V. rooms for E1,E2,E3 & W1,W2,W3 Towers Located in Podium areas.

4.0       Method

  • Storage  

Note: L.V. Panels will be offered for factory inspection/witness by Design Consultant prior to material dispatch

  • LVP’s shall be inspected upon receipt at site for damages and compliance with the approved submittals and Single line Diagram.
  • Upon completion of receiving inspection, the LVP’s shall be positioned at the respective substation locations with suitable crane arrangements.
  • LVPs found with transportation damages shall be recorded and notified to the concern party for further action.
  • LVP’s shall be covered with polythene sheets to protect from dust and moisture.

4.2       Installation

  • Ensure approved documents like shop drawing, SLD, electrical room layout and load schedules are available with the installation team.
  • Check the label/marking to ensure that it is the right panel and check the position according to the shop drawing.
  • Check the breaker rating and the provision for cable / bus bar termination.
  • Set the breaker current rating as per approved shop drawing.
  • Terminate the incoming and outgoing cable as per single line diagram using proper tools.
  • Megger the panels after connecting the compartments.
  • Megger the cables before terminating.
  • Megger the panel after termination, when I/C open and O/G closed.
  • Check working of motorized breakers.
  • Clean the termination and breaker cubicles with vacuum cleaner and hand brush to clean the dust and small metal pieces fallen during cable cutting and terminating process.
  • Ensure the busbars and interconnecting terminals are free from dust and damage.
  • Provide identification for all the cable termination as per specification requirement and SLD.
  • Dress the cables neatly with cable ties / cable cleat.
  • Double check the connections by tightening the terminations.
  • Keep the approved single line diagram near the LVP’s (photo framed), wall mounted inside the substation.
  • Inspection shall be offered for QC Verification before DEWA inspection.

6.0       Records

            6.1       QC Inspection Check List.

  • Inspection request duly signed-off by NMX and Consultant.

7.0       Attachment

  • Inspection Check List for L.V. Panels .

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.