Site icon The Engineers Blog

Method Statement For VRF SYSTEM

Method Statement For VRF SYSTEM

Method Statement For VRF SYSTEM

CONTENTS

  1. SCOPE
  2. PURPOSE
  3. RESPONSIBILITES
  4. SAFTY
  5. PROCEDURES
  6. COMMESIONING
  1. SCOPE:

The scope of this method statement covers installation of the VRF System (Refrigerant Piping Network, Piping Fittings and Transmission Networks) for all floors in accordance with specifications and drawings.

The Purpose of this method statement is to describe the materials which will be used and work procedure for VRF System.

The fixing of all air conditioning equipment, installation of all refrigerant pipe work and full commissioning shall be performed by a specialist refrigerant installer who shall be authorized to install VRF equipment

Accredited installer will ensure that all personnel are instructed to comply with the prevailing site rules/directions.

Accredited installer shall clearly state on his tender submission the specialist sub-contractor he intends to employ to carry out the work if not in their direct employment.

Full access shall be afforded to site during the installation stage of the project to allow them to verify that installation methods are fully in accordance with the supplier requirements and that the equipment’s warranties will not be invalidated. All works including labor, materials, plant, tools and equipment will comply with the standard.

Furth more all of the following points should be adhered to.

Supply and installation of all interconnecting refrigeration pipe work should be carried out by an Accredited Installer )TIBA ((certificate of approval must be submitted prior the installation commencement – the refrigeration pipes will be supplied by the manufacturer), the certificate of approval to be issued through the supplier or manufacturer representative. All pipe work must be suitable for R410a as applicable. Longest possible lengths of copper pipe should be utilized to minimize joints on site furthermore all of the following points should be adhered to.

Fig. 1- Minimum copper pipes thickness

All Completed R410 a system will be strength and leak tested with dry. If the system is found to be leaking free. The final pressure reading for both strength leaks testing is to be witnessed and entered into the supplier checklist.

3. Steps strength and leak test:

  1. 3 bar (N2) for 3 min or more ( for contractor checking before submit to consultant )
  2. 15 bar (N2) for 3 min or more ( for contractor checking before submit to consultant )
  3. 40 bar (N2) for approximate 24 hours ( for inspection from consultant side )
 

 

Electrical work contractor shall include for the design, shop drawing, material submittal and installation (unless otherwise specified). Including connecting all items of mechanical equipment. Electrical work contractor shall provide and install all wiring, cables, cable trays, termination points, and local means of Isolation, control wiring etc., to mechanical plant items to ensure that all items of equipment and controls fully function in accordance with manufacturers’ recommendations.

Thermal insulating material used within any building shall be classified as noncombustible also free from substances which in the event of a fire would generate appreciable quantities of smoke or toxic fumes. Insulating materials shall be as defined by the building regulations and as per approved material submittals.

Accredited installer will apply identification banding in all instances. Labeling will include the wording ‘Refrigerant under pressure’

Exit mobile version