METHOD STATEMENT FOR TV SPLITTER INSTALLATION AND WIRING TERMINATIONS

TV socket
TV socket

TV SPLITTER INSTALLATION AND WIRING TERMINATIONS

MATERIAL TO BE USED:-

Flush mounted TV splitter metal enclosure with size 150xl50xlOOmm manufactured by Eletra with sufficient knock outs and frame to install 2 way splitter and 6 way splitter in this enclosure.

RG 6 – C5760 Coaxial Cable is installed between individual TV outlets and 6 way splitter boxes installed in ground and first floor.

RG-11 C5034 outlet coaxial cable is installed between the dish in the roof annex floor to the 1s and ground floor splitter boxes.

RG 6 and RG 11  coaxial cables are manufactured by general cables , splitters used are 1×2 one nos and 2×6 two nos .Wisi make.

TOOLS USED:-

Cutting plier, insulation removing plier, Screw driver set

 INSTALLATIQN:-

Flush mounted metal enclosure for TV splitter boxes are installed in ground and first floor block walls in line with plaster guides and these enclosures are installed at a height of 600mm from the center of the box to finished floor level as per low current shop drawing details.

WIRING TERMINATIONS^”

RG11Satellite coaxial cable is pulled from dish at the roof annex floor to the 1st floor TV splitter box which contains 2-wav and 6 way-splitters Installed in RG-11 cable from dish is connected to the TV receiver outlet with two input points installed in first floor. From the other outlet point RG-11 cable is pulled to the input of the 2 way splitter which is installed in first floor TV splitter box.

Page 2 of3

From this 2 way splitter one cable is terminated to the input of the 6 way splitter and its 6 output are terminated with first floor individual TV outlet with RG-6 Coaxial Cable.

From the other output of 2 way slitter RG-11 coaxial cable is terminated to the ground floor input of 6 way splitter which is installed in ground floor splitter box. 6 outputs of this 6 way splitter is terminated with RG-6 Coaxial cable to the TV outlets in the ground floor.

No joints are made in the coaxial cable

All coaxial cables are terminated with special metal gland manufactured by

Wisi suitable for respective sized coaxial cables.

Printed circuit layout will be pasted inside splitter boxes

Every connected terminal in splitter boxes and respective T.V. outlets on the floor are identified by approved labels.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version