Method Statement for Storm Water and Drainage Earthwork

Manhole-Excavation
Manhole-Excavation

CONTENTS

  1. Scope of Work
  • Definitions
  • References
  • Subcontractors
  • Materials
  • Plant  & Equipment
  • Safety
  • Prior Activities
  • Procedure
  1. Responsibilities
  1. Attachments

1. Scope:

1.1This Method Statement covers the following activities related to Storm Water and Drainage works
  
 Site cleaning and grading   Trench excavation and backfill   Structural excavation and Backfill

 2. Definitions:

2.1    MS: STM  Method Statement : Storm Water and Drainage Work
  
2.2ITR  Inspection and Testing Request
  
2.3PS-GCMI  Project Specifications-General, Civil and Mechanical Infrastructure
  
2.4UG   Underground
  
2.5MDD Maximum Dry Density
  
2.6TPS    Technical  Project Specification

3. Reference

3.1GPS    General Project Specifications Section107: Clause 107.3.3 Excavation and Trenches.
  
3.2PS-GCMI  Section 200 : Clause 200.3: Excavation
  
3.3PS-GCMI  Section 901, Clause 901.3: Trench Excavation Clause 901.3.8 & 901.3.9: Backfilling to pipes and Standards of compaction
  
3.4PS-GCMI Section 200: Clause 201.3.3: Backfilling to structures
  
3.4PS-GCMI  Section 901 Clause 901.5: Testing.

 4. Subcontractors:

 N/A

 5.  Products:

5.1Pipe bedding and surround material (dependent upon pipe dia. and depth, see TPS—Section 901- Clause 901.3.6 & Clause 901.3.7and Clause 901.3.10).
  
5.2Backfill material for trench and around structure, Technical Project Specification Section 901 Clause 901.3.8 & Clause 901.3.9: Backfilling and Testing.
  
5.3Borrow material
  

 6. Tools & Equipments:

6.1Dewatering equipments & pumps (If required).
  
6.2Excavators/ JCB
  
6.3Front end loader (Shovel)
  
6.4Tipper trucks
  
6.5Small vehicles
  
6.6Soil compactor (Plate roller’s)
  
6.7Motor graders
  
6.8Surveying instruments
  
6.9Bull dozers
  
6.10Ladders
  
6.11Concrete barricades and safety equipments.
  
6.12Flagging tape/warning tape
  
6.13Water tanker
  
6.14Sheet piling & shoring materials (If required).
  
6.15Personnel protection equipments.
  
  

 7. Safety

7.1PPS Section 100: Clause 100.2 Airport Emergency and Safety.
  
7.2TPS    Technical Project Specification Section 901 Clause 901.3 : Trench Excavation and Backfill.
  
7.3Construction Safety Manual.
  
7.4Safety Hazards and Precautions
  
 a )- Strike UG Services:   Use Locator and/or hand excavation (trial holes)   b)- Excavation Collapse:   Batter sides to safe slope or provide shoring (as directed by                             Geotechnical Consultant) and subject to Engineer’s approval.   Keep vehicles/equipment safely away from excavation edge   Keep spoil at least 2.0 meter away from edges   c)- Fall into excavation:   Provide fencing, guardrails, night-time lighting and flagging tape around edges.   Provide safely fixed ladder (every 50m)   Provide banks man when operating equipment near excavation.   d)-Crane Accidents:     All cranes checked and certified     Operators professional and well experienced     Provide banks man when operating near excavation     Check load indicator, slings and wire ropes daily         e)- Falling Objects:   Stand clear during lifting operations   Wear hard hats   f)- Equipment & Vehicles:   Use Safety belts   Slow down and obey speed limits   Provide “back-ups” alarms   Provide banks man when operating equipment near excavation.   g)- Confined Space:   Check air with gas monitor before entering assembled pipeline or manholes             Check air in deep narrow trenches or excavated before entry.   Check excavations for snakes and scorpions before entry   Take precautions against flooding   Develop rescue procedures  
  

8. Prior Activities:

8.1Drawings will be checked for existing underground utilities or obstructions.
8.2A site survey will be conducted to record existing ground level conditions, mark UG utility locations, excavation limits and note obstructions.  
8.3All necessary work permits will be obtained prior to excavation (such as Notice of Intent).  
8.4Haul roads and designated disposal areas will be established.  
8.5Trial holes will be dug by hand to expose UG utilities and verify exact locations.  
8.6Additional trial holes may be dug to verify soil conditions and allow sampling and inspection by a Geotechnical Engineer where needed.
8.7Detailed drawings and calculations will be provided by a qualified engineer before commencing excavations which require a bracing and/or shoring system.

9. Procedure:

9.1Clearing & Grading  
a.After the site survey is conducted and all utilities are located and required work permits are obtained, site cleaning and grading will proceed.  
b.Any vegetation, rubbish, debris and other objectionable materials will be cleared away and hauled to designated disposal areas.  
c. The Site will then be graded to allow vehicle and equipment access.  
Note:In some cases a temporary haul road or working platform may be constructed to provide better access for vehicle and equipments.  
9.2Dewatering
  
a.Dewatering if required will be conducted according to MS-1004.
  
9.3Trench Excavation  
a.Trench Excavation will be carried out to the lines, grades and levels as shown on the drawings but shall not exceed 50 metres in advance of pipelaying unless approved by the Engineer.  
b.Equipment used for excavation will depend on the type of material to be excavated, method of hauling and site limitations.  
c.Unsuitable material will be hauled away to designated disposal areas.  
d.Suitable excavated material will be stockpiled at least 2.0 meter away from the edge of the excavation, if possible, or to an area designated by the Engineer.  
e.If necessary, the bottom of the excavation will be sloped to aid dewatering.  
f.The widths of trenches shall ensure a minimum of 150mm between the barrel of the pipe and the side of the excavation.
g.Shop drawings and calculations for any bracing and shoring if required for excavation will be submitted for the Engineer’s approval.  
h.Final excavation (last 150mm) to required grade will only be conducted shortly before bedding material or blinding concrete is placed and will be accomplished by using thin cuts with suitable equipment to avoid disturbing the formation level.  
  
Note:Excess excavation will be replaced with selected excavated material in properly compacted layers as instructed by the Engineer.  
9.4Formation or Base Preparation 
   
a.Any soft, spongy, unstable or unsuitable materials encountered at formation level will be removed and replaced with selected material in properly compacted layers. 
   
b.The bottom of all trenches (formation) will be compacted to at least 98% MDD. 
   
c.The base of all structures will be compacted to at least 98% MDD at formation level. 
   
NoteFormation inspection and compaction is a Hold Point and will be confirmed by the Consultants Inspector before proceeding with blinding concrete or bedding material. 
   
9.5Pipe Bedding and Surround 
   
a.Pipe bedding and surround will be placed in accordance to the drawings and pipe manufacturers recommendation. 
   
b.Material will comply with the requirements of Section 901 Clause 901.3.6 
       
9.6Trench Backfill 
   
a.Backfilling of trenches will comply with Clauses 901.3.8 & 901.3.9 
   
b.After the pipe surround has been placed and checked by the Consultants Inspector general backfill will proceed. 
   
c.Backfill material will be compacted to 98% MDD in max.200mm maximum loose lifts and trenches with pipeline laid shall be backfilled and hand compacted to a level of 300mm above the crown of the pipe with selected excavated material. Trenches adjacent or under roads, will be backfilled compacted to 100% of MDD and consolidated before the sub-base and pavement are laid. 
   
Note:Lifts greater than 250mm may be utilized when trials demonstrate the required compaction can be achieved. 
   
c.Suitable backfill materials will be as described in (PS-GCMI) Section 901. 
   
d.Approved marker tapes will be installed if required. 
   
9.7Structure Backfill 
   
a.Backfill adjacent to structures will proceed only after the  external protective membrane or coating has been placed, protected and checked by the Consultants Inspector. Backfilling to Structures will comply with Clause 201.3.3 
   
Note:Inspection of the structure and exterior protective membrane or coating is a Hold Point and backfilling will not proceed unless approved by the Consultant’s Inspector. 
   
b.Backfill will be placed around all sides of the structure simultaneously in order to maintain approximately the same fill height.   
c.Backfilling materials will be approved selected excavated material compacted in layers not exceeding 200mm thick to achieve a to 95% MDD. 
   

10. Responsibilities:

10.1It is the Manager’s duty to ensure that all necessary safety and protective equipment are provided along with properly trained and qualified personnel.
  
10.2It is the Site Supervisor’s duty to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also assure the method statement procedure is followed and must observe the Hold-points and notify the Consultant for inspection.
10.3It is the worker’s duty to properly wear the protective equipment provided and obey all safety rules.  He must also perform the work as described in the method statement procedure.  
10.4The Contract Manager will coordinate with Safety Engineer and ensure that the necessary resources to implement the approved method statement have been allocated to the task.  
10.5The Site Engineer will ensure that the site preparation activities are conducted according to the approved method statement.  
10.6The Material Engineer will ensure that the materials being used are in accordance to the project specifications and the approved method statement.    

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version