METHOD STATEMENT FOR INSTALLATION, TESTING & COMMISSIONING OF CLEAN AGENT SYSTEM

Wet Chemical Fire Suppression System for Kitchen Hoods

Wet Chemical Fire Suppression System for Kitchen Hoods

CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0  REFERENCES

4.0  DEFINITIONS

5.0  RESPONSIBILITIES

6.0  EQUIPMENT

7.0  PROCEDURE

8.0 ATTACHMENTS

1.0 PURPOSE

The purpose of this method statement is to outline the method for handling, storage, installation, testing and commissioning for the Clean Agent System in accordance with the requirements specified in the relevant NFPA Codes, Standards and Project specifications in all applicable areas for the project.

2.0 SCOPE

The procedure applies for the installation, testing and commissioning of 200 Bar Clean Agent INERGEN gas fire extinguishing system in at the project.

3.0 REFERENCES

4.0 DEFINITIONS:

            FF Sub-Contractor             : SUBCON

PQP                                      : Project Quality Plan

PSP                                      : Project Safety Plan

QCP                                     : Quality Control Procedure

HSE                                     : Health, Safety and Environment

MS                                       : Method Statement

ITP                                       : Inspection Test Plan

QA/QC                                : Quality Assurance / Quality Control Engineer.

WIR                                     : Inspection and Test Request

AFC                                     : Approved for Construction.

5.0 RESPONSIBILITIES:

 

            5.1 Project Manager

5.2 Construction Manager

5.3 Site Engineer

5.4 QA/QC Engineer (MEP):

5.5 Site Foreman

5.6 Safety Officer

            5.7 Store Keeper (SK)

            5.8 FF Sub Contractor

– The constant coordination with the QA/QC Engineer and the site Engineer for any works to be carried out and initiate for the Inspection for the finished works.

6.0 EQUIPMENTS:

            6.1 General Tools and Equipments:

            6.2 MATERIAL USED:

INERT GAS CLEAN AGENT (INERGEN)

Inert gas clean agent (Inergen)

Cylinder

Cylinder assembly

Distribution piping

Nozzles

OTHER ACCESSORIES

            6.3 PRESSURE TESTING EQUIPMENTS:

            6.4 Leakage Testing Tools:

            6.5 INTEGRITY TEST EQUIPMENTS:

            6.6 Pre- Commissioning Tools:

7.0 PROCEDURE

7.1 Safety

7.2 Work Sequence And Methodology

7.3 Storage

On receipt of 200 Bar INERGEN gas fire extinguishing system materials to site, precautions shall be taken for unloading, handling and storage, as follow: –

7.4 PREPARATION WORK

Before commencing the installation work of the INERGEN system, the following activities shall be ensured:

7.5 INSTALLATION ACTIVITIES

      7.5.1 INSTALLATION OF MANIFOLDS, PIPES WORK & CYLINDER BANK

7.        

7.5.2 INSTALLATION OF CABLE WORKS

7.5.3 INSTALLATION OF FIRE ALARM FIELD DEVICES & LOCAL FIRE ALARM PANEL FOR EXTINGUISHING CONTROL

7.6 FLUSHING & LEAK TESTING OF THE PIPING

7.6.1 Leakage Test Procedure:

             7.6.1.A TEST REQUIREMENTS

Before commencement of any leak testing for piping, ensure that the following are met:

            7.6.1.B TEST PROCEDURE

.

            7.7 INSTALLATION OF THE DISCHARGE NOZZLES

7.8  “Puff” Testing of the Piping

7.9 FINAL PAINTING AND IDENTIFICATION

Final Painting

Signage

       Arabic shall be provided as appropriate.

      7.10 Pressure Testing:

            7.10.1 Test Preparation:

               Before commencement of pressure testing of the manifold, the following shall be ensured:

            7.10.2 Test Procedure:

            7.11 INTEGRITY TEST:

            7.11.1 PRETEST PROCEDURE

            7.11.2  PREPARATIONS

NOTE:

The air-conditioning / ventilation system must be closed during the test. The required isolation duration will be around 2 hours for each protected area.

            7.11.3 TEST PROCEDURE

               7.11.4 Part 1: FAN TEST

            7.11.5 Part 2: COMPUTER CALCULATION

            7.11.6 INTEGRITY TEST REPORT

Upon completion of the tests, a full report shall be prepared and test results shall be compiled by the Engineer.

            7.12 Final Pre-Commissioning & Commissioning:

                7.12.1 METHODOLOGY

Before commissioning the 200 Bar INERGEN gas fire extinguishing system the following pre-commissioning checks shall be ensured: –

            7.12.1-A PRE-COMMISSIONING


 

                7.12.1-B COMMISSIONING

Operate 1 NO. of smoke detector in the protected area using a smoke gun and confirm the FOLLOWING Sequence of operations:

Operate one more detector in the protected area and confirm the FOLLOWING SEQUENCE OF OPERATIONS:

Operate the gas discharge pressure switch and confirm the following:

               Placing the system in service: