METHOD STATEMENT FOR INSTALLATION OF FIRE PROTECTION SERVICES

Fire Rating
Fire Rating

METHOD STATEMENT FOR INSTALLATION OF FIRE PROTECTION SERVICES

TABLE OF CONTENTS
Contents Page
1.0 OBJECTIVE 1
2.0 SCOPE
3.0 HANGLING AND STORAGE
4.0 WORK METHODLOGY
4.1 Rigid Coupling
4.2 Mechanical T Installation
4.3 Flexible Coupling Installation
4.4 Drop In Anchor Installation
4.5 Pipe Hanger Installation
4.6 Flanged Fittings Installation
4.7 Valve with Screw Connection Installation
4.8 Valve with Flanged End Connection Installation
4.9 Flow Switch Installation
4.10 Screw Fittings Installation
4.11 Sprinkler Head (with ceiling) Installation
4.12 Sprinkler Head (without ceiling) Installation
4.13 Pipe Sleeve Installation
4.14 Fire Protection Riser Pipe Installation
4.15 Black Pipe Painting
4.16 Black Pipe (with Undercoat) Painting
4.17 Galvanized Pipe Painting
4.18 Fire Pump Installation
4.19 FE-13 System Installation
4.20 NAF SIII System Installation
4.21 Fire Seal installation
4.22 Fireman Intercom System Installation
4.23 Fire Alarm Conduits Installation
2
5.0 HEALTH, SAFETY, SECURITY AND ENVIRONMENT
6.0 LIST OF ATTACHMENTS
7.0 INSPECTION AND TESTING
8.0 LIST OF APPENDICES
9.0 LIST OF ATTACHMENTS
3
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 4 of 46
Reference :
1.0 OBJECTIVE
This method statement is to describe s the method of which the installation
of Fire Protection Services Installation is carried out for this project.
2.0 SCOPES
This procedure applies to project site, which requires Fire Protection Services
installation work, which is carried out by the company.
3.0 HANDLING AND STORAGE
3.1 PRE- DELIVERY AND STORAGE PREPARATION.
a. Prepare delivery schedule and check site conditions as well as storage
capacity.
b. Prior to delivery of Material to site, a site survey and make all necessary
co-ordination with the main contractor as regards to access for the save
transportation of the said material to the designated location.
c. Coordinate with site workers responsible for the system installation.
3.2. INCOMING STORAGE AT SITE.
a. Check model and type of material against delivery order.
b. Check any damage during transportation.
c. If there is any evidence of damage, an internal inspection shall be made
together with supplier’s representative and the Consultant. A report shall
be submitted to the Consultant on completion of such inspection.
d. Route identification and marking work shall not be started until
coordinates with other Mechanical and Electrical Services.
e. Minor deviation from the approved construction drawing and M&E
drawing would be determined on site with the consent of consultant site
staff.
4
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 5 of 46
Reference :
4.0 WORK METHODLOGY
4.1 RIGID COUPLING INSTALLATION
1) Groove Pipe
Groove the pipe ends according to the manufacturer’s specification.
2) Check Pipe Ends
Pipe must be free from indentations, projections or roll marks on exterior
from the ends to the groove, to assure a leak tight seat fro the gasket.
Refer to Figure 1.
3) Check Gasket
Pipe must be free from indentations, projections or roll marks on exterior
from the ends to the groove, to assure a leak tight seat fro the gasket.
Refer to Figure 1.
4) Install Gasket
Place gasket over pipe ends, being sure gasket lip does not overhang pipe
end. Refer to Figure 3.
5) Join Pipe Ends
Align and bring 2 pipe ends together and slide gasket into position
centered between the grooves on each pipe. No portion of the gasket
should extend into the groove on either pipe. Refer to Figure 4.
6) Assemble Segments
Loosely assemble all segments leaving one nut and bolt off to allow for
“swing-over” feature. Refer to Figure 5.
7) Apply Housing
With 1 nut and 1 bolt removed, use the “swing-over” feature to position
housings over gasket and into the grooves on both pipes. Refer to Figure
6.
8) Insert Bolt
Insert the remaining bolt to allow easy tightening of the nut. Be sure track
head engages into housing recess. Refer to Figure 7.
9) Tighten Nuts
5
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 6 of 46
Reference :
Tighten nuts alternately and equally maintaining metal-to-metal contact
at the angle bolt pads. Tighten securely to assure a rigid joint. Refer to
Figure 8.
TECHNICAL INFORMATION FOR RIGID FITTING
· Manufacturer : Victaulic
· Model : Fire Lock (Style 005)
· Material : Ductile Iron
· Size : 65mm dia. to 200mm dia.
· Approval : UL/FM/ULC
6
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 7 of 46
Reference :
7
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 8 of 46
Reference :
4.2 MECHANICAL-T INSTALLATION
1) Drill Hole
Drill the hole according to the manufacturer’s specification. Hole
size refer to appendix 1.
2) Prepare to Assembly
Remove 1 nut and bolt from housing. Loosen the other nut until it
is flush with the end of the bolt. Remove the tape and lift the
gasket from Mechanical-T outlet. Refer to Figure 1.
3) Check Gasket & Lubricants
Check gasket supplied to be certain it is suited for intended service.
Apply a thin coat of silicone lubricant to gasket lips and outside of
gasket. Refer to Figure 2.
4) Position Gasket
Reposition gasket into housing using alignment tabs on slides for
proper positioning. Refer to Figure 3.
5) Position Mechanical-T
a) (Style 920) Rotate the lower housing approximately 90 degree
away from the upper housing. Place the upper section onto the
face of the pipe in line with outlet hole. Rotate the lower section
around the pipe end and close the 2 halves.
b) (Style 921) Place the upper section onto the face of the pipe
with the locating collar engaging into the hole. Slide U-bolt end
with nut into slot, swing opposite end into other slot. Apply nut
and tighten both sides evenly until finger tight.
6) Check Locating Collar
Make sure that the locating collar is in the outlet hole by rocking the
upper housing in the hole. Refer to Figure 5.
7) Insert Bolt
Insert bolt in its hole and finger tighten both nuts. Be certain ovalneck
of bolt engages recess in housing. Make sure that the locating
collar is in the outlet hole and the positioning lugs are properly
aligned.
8) Tighten Nuts
8
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 9 of 46
Reference :
Tighten bolt nuts uniformly until the upper housing is in complete
surface contact in the gasket pocket area and the assembly is rigid.
TECHNICAL INFORMATION FOR MECHANICAL-T FITTING
· Manufacturer : Victaulic
· Model : Style 920 and Style 921
· Material : Ductile Iron
· Size : 65mm dia. to 200mm dia.
· Approval : UL/FM/ULC
9
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 10 of
46
Reference :
10
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 11 of
46
Reference :
4.3 FLEXIBLE COUPLING INSTALLATION
1) Groove Pipe
Groove the pipe ends according to the manufacturer’s specification.
2) Check Pipe Ends
Pipe must be free from indentations, projections or roll marks on
exterior from the ends to the groove, to assure a leak tight seat fro
the gasket. Refer to Figure 1.
3) Check Gasket & Lubricant
Check gasket supplied to be certain it is suited for intended service.
Apply a thin coat of silicone lubricant to gasket lips and outside of
gasket. Refer to Figure 2.
4) Install Gasket
Place gasket over pipe ends, being sure gasket lip does not
overhang pipe end. Refer to Figure 3.
5) Join Pipe Ends
Align and bring 2 pipe ends together and slide gasket into position
centered between the grooves on each pipe. No portion of the
gasket should extend into the groove on either pipe. Refer to Figure
4.
6) Apply Housing
Place housings over gasket, being sure the housing keys engage
into grooves.
7) Apply Nuts
Insert nuts and apply nuts finger tight.
8) Tighten Nuts
Tighten nuts alternately and equally until housing bolt pads are
firmly together metal-to-metal. Excessive nut tightening is not
necessary.
11
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 12 of
46
Reference :
TECHNICAL INFORMATION FOR FLEXIBLE COUPLING
· Manufacturer : Victaulic
· Model : Style 75 Flexible Coupling
· Material : Ductile Iron
· Size : 65mm dia. to 200mm dia.
· Approval : UL/FM/ULC
12
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 13 of
46
Reference :
4.4 DROP IN ANCHOR INSTALLATION
1) Marking
Identify the actual location of the hanger based on the approved
shop drawing. Mark the position for installing the drop in anchor.
2) Confirm Hole of Depth
Check the hanger size to confirm the depth of the hole to be drilled
based on approved shop drawings and manufacturer’s specification.
3) Drill Hole
Check the hanger size to select the right drill bit. Then drill the hole
according to the manufacturer’s specification on the marked
position. Refer to Figure 1.
4) Cleaning
Clean the drilled hole to ensure it is free of dust. Refer to figure 2.
5) Insert drop in Anchor
Insert the drop in anchor into the hole. Refer to figure 3.
6) Hammering
Hammering down the conical plug inside the anchor with setting
punch. Refer to figure 4.
7) Install Hanger Rod
Install the hanger rod into the drop in anchor. Refer to figure 5.
4.5 PIPE HANGER INSTALLATION
13
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 14 of
46
Reference :
1) Confirm Location
Identify the actual location of the hanger based on the approved
shop drawing. Mark the position for installing the drop in anchor.
2) Install Drop in Anchor
Install drop in anchor. (Please refer to Method Statement for Drop in
Anchor Installation) Refer figure 1.
3) Install Pipe
Install the pipe either by screw fitting or welding. Refer to figure 2.
4) Install Hanger Rod
Select the hanger based on the pipe size. Install the hanger rod to
the drop in anchor.
5) Install Hanger
Install the hanger to the pipe and the hanger rod. Refer to figure 3.
6) Tightening
Tighten the bolts and nut that hold the hanger rod and hanger
evenly.
TECHNICAL INFORMATION FOR PIPE HANGER
14
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 15 of
46
Reference :
· Manufacturer : UBE Industries (Malaysia)
· Model : Ring Hanger
· Material : Mild Steel
· Finishes : Galvanized Plated
· Size : 15mm dia. to 200mm dia. pipe size
SCHEDULE OF PIPE HANGER SPACING AND ROD SIZE
Pipe Diameter (mm)
Maximum Hanger Spacing
(mm)
Rod Size (mm)
12 3000 10
25 3000 10
32 3000 10
40 3000 10
50 3000 10
65 3000 10
80 3000 10
100 3000 10
150 3000 12
200 3000 12
15
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 16 of
46
Reference :
16
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 17 of
46
Reference :
4.6 FLANGE FITTING INSTALLATION
1) Select Flange
Check the flange size and specification according to pump size and
valve size, for example Table E, Table F etc. refer to appendix 1.
2) Fabricate Pipe
Cut the pipe to the required length. Refer to figure 1.
3) Jointing
Jointing the flange to either valve or pump. (Please refer to the
Method Statement for Valve with Flange End Connection
Installation). Refer to figure 2.
17
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 18 of
46
Reference :
18
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 19 of
46
Reference :
4.7 VALVE with SCREW CONNECTION INSTALLATION
1) Select Valve
Confirm the valve size and location based on the shop drawings.
Ensure that the selected valve is screw type.
2) Fabricate Pipe
Cut the pipe to the required length and thread it accordingly.
Attached the threaded table at appendix 1.
3) Positioning
Place the valve between the pipe and make sure the threads are
free of dust. Refer to figure 1.
4) Jointing
Guide one of the pipe ends onto the valve’s thread, slowly run pipe
in clock-wise direction. Refer to the figure 2.
5) Tightening
Hold the valve firmly by a spanner on the flat nearest joint and then
rotate the pipe with a plumbing wrench. Rotate the pipe until the
end of the spindle operating joint. Repeat the above steps for the
other pipe. Refer to figure 3.
19
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 20 of
46
Reference :
20
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 21 of
46
Reference :
4.8 VALVE with FLANGE END CONNECTION INSTALLATION
1) Select Valve
Confirm the valve size and location based on the shop drawings.
Ensure that the selected valve is flange type.
2) Positioning
Place the valve between the pipe flanges. Make sure the flange and
adjacent pipe work are clean of dirt. Refer to figure 1.
3) Select Gasket
Select the gasket size according to the valve size and associated
pipe size based on approved shop drawings so that it can match the
pipe work flange. Refer to figure 2.
4) Connecting
Connect the valve with the pipe flange. The pipe flange shall be
square with the associated pipeline. Refer to figure 3.
5) Tightening
When the valve is in proper position, install the bolts into the holes.
Tightening the nuts one by one evenly. Repeat the above steps for
the other joint. Refer to figure 4.
21
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 22 of
46
Reference :
22
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 23 of
46
Reference :
4.9 FLOW SWITCH INSTALLATION
1) Select Flow Switch
Confirm the valve size and location based on the shop drawings.
Ensure that the selected valve is flange type.
2) Confirm Location
Place the valve between the pipe flanges. Make sure the flange and
adjacent pipe work are clean of dirt. Refer to figure 1.
3) Drill Hole
Select the gasket size according to the valve size and associated
pipe size based on approved shop drawings so that it can match the
pipe work flange. Refer to figure 2.
4) Cleaning
Clean the inside pipe of all growth or other materials for a distance
equal to the pipe diameter on either side of the hole.
5) Invert Vane
Roll the vane so that it may be inserted into the hole, do not bend
or crease it. Insert the vanes so that the arrow on the saddle points
in the direction of water flow. Refer to figure 2.
6) Tightening
Install the saddle points and tightening the nuts alternatively. The
vane must not rub the inside of the pipe or bind in any way. Refer
to figure 3.
Pipe Size Hole Size
2” to 2 ½ “ 1 ¼ “ + 1/8” – 1/16”
3” to 10” 2” + 1/8”
23
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 24 of
46
Reference :
TECHNICAL INFORMATION FOR FLOW SWITCH
· Manufacturer : Potter (USA)
· Model : VSR – F
· Material : Vane
· Size : 65mm dia. to 150mm dia.
· Approval : UL/FM/ULC
24
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 25 of
46
Reference :
25
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 26 of
46
Reference :
4.10 SCREW FITTING INSTALLATION
1) Check Pipe Length
Check the pipe length required based on the approved shop
drawing.
2) Marking & Cutting
Mark the desired length on the pipe and cut it by using a hacksaw.
Make sure the pipe is perpendicular to the hacksaw cut. Refer to
Figure 1.
3) Threading
Place the pipe in the threading machine and thread it accordingly.
Make sure the thread of the pipe is in good condition. Refer to
Figure 2.
4) Wrap Teflon Tape
Remove the oil from the pipe end after the threading procedure and
wrap it with Teflon tape. Refer to Figure 3.
5) Installation
Install the pipe to the screw fitting. Refer to Figure 4.
26
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 27 of
46
Reference :
27
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 28 of
46
Reference :
4.11 SPRINKLER HEAD with CEILING INSTALLATION
1) Select Sprinkler Head & Confirm Location
Select the sprinkler head according to the approved materials list
and ensure that the sprinkler head positions are based on the
approved shop drawing.
2) Check Ceiling Tee Installation
Ensure the ceiling tee is being installed and leveled 9by other).
3) Install Dropper
Install the dropper pipe to the sprinkler range pipe.
4) Cleaning
Clean the screw fitting and sprinkler tee joint to ensure they are
free of dust.
5) Wrapping
Wrap the screw joint of the sprinkler head Teflon tape to prevent
leaking.
6) Tightening
Install the sprinkler head rosette and sprinkler head to screw joint of
the dropper pipe. Then, tighten the sprinkler head into the screw
fitting by using wrench.
7) Levelling
Ensure the sprinkler head is level against the ceiling board.
28
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 29 of
46
Reference :
4.12 SPRINKLER HEAD without CEILING INSTALLATION
1) Select Sprinkler Head & Confirm Location
Select the sprinkler head according to the approved materials list
and ensure that the sprinkler head position are based on the
approved shop drawing.
2) Cleaning
Clean the screw fitting and sprinkler tee joint to ensure they are
free of dust.
3) Wrapping
Wrapping the screw joint of the sprinkler head Teflon tape to
prevent leaking.
4) Tightening
Then tightening the sprinkler head into the screw fitting by using
wrench.
4.13 PIPE SLEEVE INSTALLATION
1) Confirm Location
Check the approved shop drawings for the actual location of the
pipe sleeve to be provided.
2) Marking
Mark the location of the pipe and identify the size of pipe sleeve to
be provided. (Note : The pipe sleeve should be 1 pipe size bigger
than the actual pipe running)
3) Submit for Approval
Then, the location and size of pipe sleeve to be provided shall be
submit to Consultant approval.
4) Install
Upon approval, the pipe sleeve shall be provided before the
concreting.
29
Company
METHOD STATEMENT
Title : Method Statement for Fire Protection
Services Installation
Page : 30 of
46
Reference :
4.14 FIRE PROTECTION RISER PIPE INSTALLATION
PURPOSE
This method statement defines the methods and sequence to be carried out
for the installation of Fire Protection Riser Pipe to ensure they are in
compliance with contract requirements, technical specifications and quality
management.
SCOPE
This shall cover all the Fire Protection System, i.e. Sprinkler System, wet Riser
and Hose Reel System.
PROCEDURE
1) Check Location of Riser

  1. Confirm the location of riser based on approved / coordinated shop
    drawings.
  2. Check whether any opening through slabs (either box-up or pipe
    sleeves) is provided.
  3. Check the size of the opening. If the opening size is not sufficient or
    opening is not provided, request permission for coring from the Main
    Contractor.
  4. Core opening once approval is obtained.
    2) Fabrication of Pipe
  5. Fabricate pipes
    3) Hoisting of Pipe
  6. Book the Materials Hoist or Tower Crane fro hoisting the pipes to the
    designated floors.
  7. Position the pipes at the area allocated by the Main Contractor.
    30
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 31 of
    46
    Reference :
    4) Install Riser Pipe
  8. Confirm the location of riser based on approved / coordinated shop
    drawings.
  9. Lower down the pipe off any unwanted materials and rubbish from the
    riser shaft.
  10. If box opening is provided, slip a piece of pipe sleeve onto the pipe.
  11. Coupled the pipe with previously installed pipe with a flexible coupling.
    (Please refer to Method Statement for the installation method of
    flexible coupling).
  12. Pull upwards the newly installed pipe using the chain block. This is to
    allow pipe movement during the building shrinkage.
  13. Align the pipe vertically with spirit level.
    5) Install Riser Pipe Bracket
  14. Once the pipe has been aligned, install the pipe bracket to support the
    riser pipe.
  15. If box opening is provided, install temporary bracket to the pipe.
  16. Cast the opening and ensure the pipe sleeves are installed prior to
    casting.
  17. Once the concrete has cured, dismantled the temporary bracket and
    replace it with a permanent bracket.
    6) Install Fire Barrier
  18. Install Rock Wool into the gap between the riser pipe and the pipe
    sleeve as per contract requirement. The Rock Wool will act as fire
    barrier in the case of fire.
    31
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 32 of
    46
    Reference :
    INSTALL PERMANENT
    BRACKET
    BOX OPENING ?
    START
    CHECK RISER LOCATION
    SLAB OPENING SUFFICIENT?
    FABRICATE PIPES
    YES REQUEST FOR CORING
    NO
    CORE OPENING
    HOIST PIPE
    INSTALL TEMPORARY
    BRACKET
    CAST BACK OPENING
    REMOVE TEMPORARY
    BRACKET
    INSPECTION
    PRESSURE TEST
    END
    FLOW CHART FOR RISER PIPES INSTALLATION
    32
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 33 of
    46
    Reference :
    4.15 BLACK PIPE PAINTING
    1) Clean the Black Pipe
    Clean the black pipe with cotton rag to remove any dust or grease
    on the pipes.
    2) Paint the Pipe with Red Oxide
    After cleaning, paint the black pipes with 1 layer undercoat of Red
    Oxide Primer. Please ensure both sides (top & bottom) are painted
    evenly.
    3) Wait for Dry
    Put the painted pipes ina good ventilation condition for 24 hours for
    the pant dry.
    4) Paint with Finish Coat
    After the paint is dried, then paint the pipes with 1 layer of finish
    coat (Nippon 9000, Flamengo 1420). Please ensure both sides (top
    & bottom) are painted evenly.
    5) Install the Pipe
    After the finish coat dry, install the pipes.
    6) Paint Final Layer
    After installation, paint the final layer of paint (Nippon 9000,
    Flamengo 1420) to the installed pipes. Please ensure both sides
    (top & bottom) are painted evenly.
    4.16 BLACK PIPE with UNDERCOAT PAINTING
    1) Clean the Undercoat Black Pipe
    Clean the undercoat black pipes with cotton rag to remove any dust
    on the pipes.
    33
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 34 of
    46
    Reference :
    2) Paint with Finish Coat
    After cleaning, paint the black pipes with 1 layer finish coat (Nippon
    9000, Flamengo 1420) on both sides of pipes.
    3) Install the Pipe
    After the finish coat dry, install the pipes.
    4) Paint Final Layer
    After installation, paint the final layer of paint (Nippon 9000,
    Flamengo 1420) to installed pipes. Please
    4.17 GALVANIAED PIPE PAINTING
    1) Clean the Galvanized Pipe
    Clean the galvanized pipe with cotton rag to remove any dust or
    grease on the pipes.
    2) Paint the Pipes with Zinc Chromide
    After cleaning, paint the galvanized pipes with 1 layer undercoat of
    Zinc Chromide Primer. Please ensure both sides (top & bottom) are
    painted evenly.
    3) Wait for Dry
    Put the painted pipes in a good ventilation condition for 24 hours for
    the paint dry.
    4) Paint with Finish Coat
    After the paint dried, then paint the pipes with 1 layer of finish coat
    (Nippon 9000, Flamengo 1420). Please ensure both sides (top &
    bottom) are painted evenly.
    5) Install the Pipes
    After the finish coat dry, install the pipes.
    6) Paint Final Layer
    After installation, paint the final layer of paint (Nippon 9000,
    Flamengo 1420) to the installed pipes. Please ensure both sides
    are painted evenly.
    34
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 35 of
    46
    Reference :
    4.18 FIRE PUMP INSTALLATION
    1) Pump Plinth
    Ensure pump plinth provided according to the specification and
    clearly status in the drawing.
    2) Inspect Inertia Block
    Inspect inertia block deliver and ensure it according to the
    specification.
    3) Inspect Spring Isolator
    Inspect spring isolator deliver. Ensure it is according to the
    specification.
    4) Fire Pump Inspection
    Ensure all the fire pumps deliver are according to the specification.
    Each pump deliver to site will be provide with a copy of approved
    test certificate.
    5) Fire Pump Installation
    Install the fire pump according to the procedures below:
    a) Provide the pump plinth
    b) Install the Spring Isolator according to the mounting with the
    inertia block.
    c) Mount the inertia block on top of the spring isolator.
    d) After that mount the fire pump base on top of the inertia block.
    e) Check all seal, glands and pipeline for leaks.
    f) Check all pump bearings and lubricate with oil or grease as
    necessary.
    g) Check the alignment and condition of all rubber coupling
    between pumps and drive motors.
    h) Check all bolts and nuts for tightness and tighten as necessary.
    35
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 36 of
    46
    Reference :
    4.19 FE 13 SYSTEM INSTALLATION
    1) Material Inspection
    Inspect all the materials deliver for install the FE 13 system are
    following the specification.
    2) Inspect Piping Installation
    Ensure all the piping install in the FE 13 system are following the
    drawing. Ensure that pipe brackets/hanger are installed every 3
    meter.
    3) Insert Wiring Installation
    Inspect all the surface conduiting and wiring install in the FE 13
    system protected rooms are according to the specification and
    approve drawing.
    4) FE 13 Cylinder Installation
    Install the FE 13 cylinder according to the detail FE 13 system
    installation in the approve drawing. Ensure each of the cylinder are
    fully charged.
    5) FE 13 Panel Installation
    Ensure the FE 13 panel and key switch are install according to the
    FE 13 system layout in that room. Test the key switch. Repeat the
    test for 5 times.
    6) Testing & Commissioning
    After completed all the installation, clean out the internal surface of
    pipework by purging air. Ensure that the system is working by
    doing the internal testing.
    36
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 37 of
    46
    Reference :
    4.20 NAF SIII SYSTEM INSTALLATION
    1) Material Inspection
    Inspect all the materials deliver for install the NAF SIII system are
    following the specification.
    2) Inspect Piping Installation
    Ensure all the piping install in the NAF SIII system are following the
    drawing. Ensure that pipe brackets/hanger are installed every 3
    meter.
    3) Insert Wiring Installation
    Inspect all the surface conduit and wiring install in the NAF SIII
    system protected rooms are according to the specification and
    approve drawing.
    4) NAF SIII Cylinder Installation
    Install the NAF SIII cylinder according to the detail NAF SIII system
    installation in the approve drawing. Ensure each of the cylinder are
    fully charged.
    5) NAF SIII Panel Installation
    Ensure the NAF SIII panel and key switch are install according to the
    NAF SIII system layout in that room. Test the key switch. Repeat
    the test for 5 times.
    6) Testing & Commissioning
    After completed all the installation, clean out the internal surface of
    pipework by purging air. Ensure that the system is working by
    doing the internal testing.
    37
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 38 of
    46
    Reference :
    4.21 FIRE SEAL INSTALLATION
    1) Installed Pipe Sleeve
    Install pipe sleeve with radius 25mm bigger than fire protection
    pipe.
    2) Inspect Pipe & Sleeve
    Ensure pipe sleeve or galvanized sheet are installed with a proper
    gap spacing.
    3) Insert Rockwool
    Insert Rockwool to the center area in between sleeve and pipe and
    create a tight bond.
    4) Apply Sealant
    Apply fire sealant to the front gap of pipe sleeve. Ensure minimum
    sealant penetration depth should not less than 12mm.
    5) Touch-Up
    Ensure the fire sealant have filled all the visible gap and make a
    smooth surface finishes.
    6) Indicator
    Apply sticker to the pipe sleeve to indicate location, type of services
    and personal involved in the above works.
    38
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 39 of
    46
    Reference :
    4.22 FIREMAN INTERCOM SYSTEMS INSTALLATION
    OBJECTIVE
    This method statement is to ensure the contractor to carry out work done
    according the specification the specification approved by consultant.
    SCOPE
    The contractor shall supply and install in accordance with the specification of
    material and workmanship, the fireman intercom systems, underground and
    aboveground pipe work and electrical work.
    REFERENCE
    · Catalogue
    · Specification
    · Drawing
    RESOURCES
    1) Material
    Item Description Manufacturer (brand)
    1.0 Fireman Intercom System Mictron 8
    39
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 40 of
    46
    Reference :
    2) Machinery Tool Equipment
    3) Manpower
    HANDLING & STORAGE
    The contractor shall supply and install in accordance with the specification of
    material and workmanship, the fireman intercom systems, underground and
    aboveground pipe work and electrical work.
    WORK METHODOLOGY
    1) Procedures
    a) Wiring installation work procedure is as the following;
    i) The preparation of wiring installation working drawing,
    technical data catalog are to be in conducted simultaneously
    after the finalization and approval of design drawing.
    ii) After the approval working drawing and technical data
    catalogs, the contractor shall proceeds with the procurement
    of all related equipment and materials for wiring installation
    work.
    b) Installation of the remote station box
    i) Remote Station box should be installed at 1800mm height
    from the finished floor level at escape staircases, lift motor
    room, gen-set room of fire safe lobby.
    Item Description Manufacturer (brand)
    1.0 Testing & Commissioning Systems Multi Meter
    No. Designation No. Of Personal
    40
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 41 of
    46
    Reference :
    INTRODCUTION
    Microprocessor based Fireman Intercom System
    The fireman intercom system is designed to be used by fireman for two-way
    communication during fire situation or emergency.
    1) The system consist of 2 sections;
    a) Main Fireman Intercom Panel (MFIP).
    i) To be situated at the Fire Control Room
    ii) This is command center where all calling and receiving of Remote
    Fireman Intercom Stations (RFIS) are monitored and controlled.
    All the data (calling and receiving signals) are processed into
    audio and visual.
    iii) The MFIP consists of the following;
    · LED indicators
    · An audible warning device (buzzer)
    · A DC Voltmeter
    · A 16 x 1 character LCD (Liquid Crystal Display) for text display
    · An operator keyboard for command entry
    · Master Handset
    · Intercom Status Panel indicating the RFIS’s zone
    b) Remote Fireman Intercom Stations (RFIS)
    i) To be situated at fire escape routes, such as escape staircase and
    fire safe lobbies.
    ii) It consists of red colour handset complete with a dynamic receiver
    and condenser microphone transmitter. The handset is housed
    red metal cabinet with glass front panel, a break glass and key
    operated door.
    iii) Calling and fault condition of all RFIS are monitored at the MFIP.
    c) Remote Telephone Terminal Unit (RTTU)
    41
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 42 of
    46
    Reference :
    i) To be situated at any of the suitable area, i.e. telephone or
    electrical riser.
    ii) It consist of red color box complete with zone card termination
    card.
    iii) One RTTU can be linked to a maximum of 10 RFIS per set.
    2) All the RFIS are to be terminated to the RTTU by 1 pair of PVC cable
    1.5mm-sq each.
    3) Wiring from the RTTU (Remote Telephone Terminal Unit) to the Main
    Fireman Intercom Panel are:
    a) 1 pair twisted and screened (5.4mm2) for data transmission.
    b) 1 pair RVC cable (2.5mm2) for speech line.
    c) 1 pair PVC cable (2.5mm2) for power supply.
    TESTING & COMMISSIONING PROCEDURES
    1) Minimum of two people are required for the testing. One stationed at the
    Fireman Intercom Panel and the other at any chosen Remote Fireman
    Intercom Station to actuate calls.
    2) Check all indicating light on the Main Fireman Intercom panel console are
    in good condition.
    3) Calling from the master handset to remote intercom station;
    a) Pick-up the master handset, key-in the remote station’s zone number
    at the keypad. (Example : Zone 12. Press ‘Call’ Key, followed by ‘12’
    and enter key).
    b) Led at the remote handset box will light up Check the correct remote
    station at the zone.
    c) Open the remote handset box, pick-up the handset. Two-way
    communication should establish.
    42
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 43 of
    46
    Reference :
    4) Calling from any remote intercom station to the Main Fireman Intercom
    panel;
    a) Open the remote handset station box and pick up the handset,
    call led at the MFIP should blinked and buzzer ring continuously.
    b) Check the correct zone’s calling at the Main Fireman Intercom
    Panel.
    c) To establish the call. Pick up the master handset.
    5) Conference call or party lines can be generated from master handset or
    remote stations – Maximum of 9 remote fireman intercom + 1 master
    handset can communicate simultaneously.
    a) Refer to ‘CALL’ procedure (8.3 or 8.4)
    b) During Conferencing, the master panel can terminate any calls
    of the remote station by pressing the ‘CUT’ key.
    c) The master panel can also establish new outgoing or incoming
    calls by following the ‘CALL procedures’ and the first received
    call will be cut-off.
    6) Reset the system and return it to normal position.
    ATTACHMENT
    1) Fireman Intercom – Installation & termination at Remote Fireman Intercom
    Handset.
    2) Installation of Remote Fireman Intercom Box
    3) Checklist of Testing & Commissioning – Fireman Intercom System.
    43
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 44 of
    46
    Reference :
    CONDUIT INSTALLATION
    1) MEASUREMENT / LOCATION OF G.I. CONDUIT AND MARKING OF CONDUIT ROUTE.
    a) Site supervisor will study and counter check the proposed locations of the
    conduit as shown on the shop drawing. Ensure proper coordination with the
    Main Contractor and other trades to optimize the space allocation and proper
    conduits management.
    b) Site supervisor will measure the length of G.I. conduit required for installation
    at site and instruct the workers to prepare these conduits. Installation will be
    carried out in a planned and timely fashion so as not to delay works by other
    trades.
    c) For horizontal installation of conduits, straight lines are marked by using
    string coated with white powder, tied to the nails at both ends. Ensures
    appropriate string tension by plucking and releasing the string before
    44
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 45 of
    46
    Reference :
    drawing the straight line. Repeat the steps above for vertical surface
    installation.
    2) FIXING OF SURFACE G.I. CONDUIT
    a) After dismantling the strings and the nails, drill holes along the white lines.
    Insert the drop-in anchor bolt into the holes before installing the rods.
    b) Clip the G.I. conduits to the rods by using fasteners.
    c) If necessary, the G.I. conduit will be cut to length required and threaded.
    Threading will be process by stocks and dies. Rotate the stocks and dies two
    and a half turns in a clockwise direction and the in a counter clockwise
    direction, to clear away the accumulated swart. This will enable the tread to
    be cut cleanly and efficiently without fear of stripping. Once completed, file
    across the leading edge of the thread and reamer the inner periphery. This
    prevents cable snagging on burred edges.
    d) Conduit sockets complete with thread joint two length of conduits. In case of
    crossing or ending or at ‘T’ junction area, cross-boxes, “Tee” boxes, “Trough”
    boxed are normally used to link up conduit pipes.
    e) As soon as the conduits are fixed, site supervisor will check and inspect the
    site to ensure that installations are according to the shop drawings. A formal
    request will be extended to the Resident Engineer.
    3) STANDARD AND CERTIFICATION
    a) Ensure that the capacities of trunkings and conduits provided are adequate
    to cater all wirings with a minimum spare space of 40%.
    4) METHOD OF FIXING OF CONCEALED G.I CONDUITS
    a) Place the conduits between the two layers of slab rebar or behind the column
    rebars from dropper to socket outlet points.
    b) Ensure that conduits, inspection boxes, back boxes and all other accessories
    used are rigidly secured to the rebar and all joints are firmly tightened before
    concreting.
    45
    Company
    METHOD STATEMENT
    Title : Method Statement for Fire Protection
    Services Installation
    Page : 46 of
    46
    Reference :
    c) Site supervisor must ensure that preventive measures are taken to keep
    concrete and unwanted materials from getting into the conduit by
    temporarily sealing off the open-ended conduits with tape.
    5) METHOD OF FIXING THREADED CONDUIT AT ENTRIES INTO FAS PANEL
    6) METHOD OF FIXING CONDUIT INTO CIRCULAR BOX
    7) MAXIMUM ALLOWANCE SPACING BETWEEN TWO INSPECTION BOXES OR
    CIRCULAR BOXES SHALL NOT BE MORE THAN 9M STRAIGHT RUN.
    8) BENDING OF CONDUIT
    9) SUPPLEMENTARY SUPPORT AND SPACING OF SUPPORT FOR CONDUITS

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version