Method Statement for Construction of North Stormwater Retention Pond and Overtopping Spillway

ACTIVITY HAZARD ANALYSIS Construction of North Stormwater Retention Pond and Overtopping Spillway

ACTIVITY HAZARD ANALYSIS Construction of North Stormwater Retention Pond and Overtopping Spillway

CONTENTS

  1. Purpose
  1. Responsibilities
  1. Attachments
  1. Purpose

1.1       To ensure that the North Stormwater Retention Pond and Overtopping Spillway are executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

9.1       Excavation

            9.3       Casting of Concrete Grade 40/20/SF

9.4       Placing of 125mm thick Quarried Rock at the top 1.5m of the Pond

            9.5       Fixing of Precast Kerb

9.5.1       The kerb blinding grade 40/20/S, 200mm minimum thickness, shall be cast to the lines and grades indicated on the approved shop drawings.

9.5.2       Precast half batter kerb (150X305 mm), conforming to BS 7263, shall be laid on 15mm thick 3:1 sand/ cement mortar bed.

9.5.3       A10mm compressible waterproof joint filler shall be provided at every tenth joint, or as directed on site, to accommodate expansion.

9.5.4       After checking of kerb by the Engineer, the hunching shall be cast by using concrete grade 40/20/S.  The blinding and hunching of the kerb shall have expansion joints with 10mm joint filler at agreed intervals.

.

10.0  Responsibilities

  1. The CM will coordinate with SE and ensure that necessary resources to implement the approved method statement, JHA, and AHA have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA and AHA.  The SE will also ensure that all in-situ tests, as required by the ITP, are implemented.
  1. The ME will ensure that the materials being used are in accordance with the project specifications and the approved material submittals.
  1. It is the site supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized.  He must also ensure that the AHA and JHA are implemented and the approved method statement procedure is followed and the ITP is applied.