Site icon The Engineers Blog

Method Statement for Construction of AGL Ducts and Installation of Precast AGL Lighting Pits

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

CONTENTS

  1. Scope of Work
  1. Responsibilities
  1. Attachments


  1. Scope of Work
  1. This procedure is applicable to the following works associated with the project titled, “New 2k Runway- Main Runway Works” – Contract Number NRTW-1008-CN.
  1. This method statement outlines the procedures to be followed in the construction of AGL future ducts & installation of precast AGL pits at locations shown in the contract drawings and as directed by the Engineer.

The following six sizes of ducts shall be constructed in this contract, with the ones underneath the pavements surrounded by concrete of grade 40/20/S and the ones at all other locations by concrete grade 30/20/S.

                        –           1 Way x 50mm diameter PVC duct

                        –           1 Way x 100mm diameter PVC duct

                        –           2 Way x 100mm diameter PVC duct

                        –           4 Way x 100mm diameter PVC duct

                        –           10 Way x 100mm diameter PVC duct

                        –           15 Way x 100mm diameter PVC duct

            2.5                   ESHO              Environmental, Safety and Health Officer

            2.6                   ITP                              Inspection Testing Plan

            2.7                   PPE                 Personal Protective Equipment

            2.8                   AHA                 Activity Hazard Analysis

            2.9                   JHA                 Job Hazard Analysis

3.1                   Specifications:             Volume 3 – Section 9 – Part A

3.2                   Drawings:                                Volume 2 – Section 8 – Parts B and F

3.3                   BOQ:                                       Bill No. 5

None

5.2                   Concrete grades 50/20/R, 40/20/S, 30/20/S, & 45/10/C

5.3                   Draw ropes

            5.4                   End caps

            5.5                   Polythene sheet

            5.6                   Formwork/Shuttering

            5.7                   Warning tapes

            5.8                   Traffic cones

            5.9                   Traffic signs

            5.10     Safety barrier

            5.11     AGL Pits

6.1                   Excavator

            6.2                   Lifting equipment IT-28 with hydraulic boom

            6.3                   Hand shovel

            6.4                   Small generator

            6.5                   Concrete plant

            6.6                   Transit mixer

            6.7                   Concrete vibrator

            6.8                   Air compressor

            6.9                   PPE (Personal Protective Equipment)

9.1                   Installation of Precast AGL Pits

9.2                   Construction of AGL Ducts

Note    

In other locations, except beneath all pavements, the standard duct bank details shall be used as shown in the drawings and the surround concrete shall be grade 30/20/S.

  1. Responsibilities
  1. The CM will coordinate with SE and ensure that the necessary resources to implement the approved method statement, Job and Activity Hazard Analysis have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement, JHA, AHA and all in-situ tests as required in the ITP are implemented.
  1. The ME will ensure that the materials being used are in accordance to the project specifications, the approved method statement and the ITP.

It is the Front Line Site Supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are properly utilized.  He must also assure the AHA and JHA are implemented and the method statement procedure is followed and the ITP is applied.

Exit mobile version