Regarding material stock at site and our previous communication about the payment steel against delivery

Rebar on construction site
steel rebar for reinforcement concrete at construction site with house under construction background

Date: xxx

Ref: CC/269/CM/32

To                          : M/s. xxx, Dubai, UAE

Kind Attn              : Mr. xxx

Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al        Barsha 1st, Dubai U.A.E.

Subject                 : Regarding material stock at site and our previous communication about the payment steel against delivery

Dear Sir,

With reference to the above, we would like to inform you that as per discussion, we received all steel at site and because of the space issue, we shifted partial stock to other location.

We would like to inform you that if any issued for pay against full delivery of the steel.

Kindly release the amount only for material at site (steel stock at site)

This is for your kind information and do the needful as well as we apologize for any misunderstanding full material delivered/shifted and available at site and payment requested

Thanking you,

For xxx Contracting L.L.C

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version