material stock at site and payment steel against delivery

Rebar on construction site
steel rebar for reinforcement concrete at construction site with house under construction background

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject              : Regarding material stock at site and our previous communication about the payment steel against delivery

Dear Sir,

With reference to the above, we would like to inform you that as per discussion, we received all steel at site and because of the space issue we could not keep the stock at site which was explained in our previous communication.

We would like to inform you that if any issued for pay full, please release only for the material stock at site.

This is for your kind information and do the needful.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.