Manpower Requirement

Construction Labor
Construction Labor

Date: 20.02.2017

Kind Attn:       Mr. xxx| Mr. xxx| Mr. xxx

Project:         2B + G + 14 + Lower Roof Hotel Building

Plot No.:        373-1297 at Barsha, Dubai

Subject:       Manpower Requirement

Dear Sir,

Good Day!

Pertaining to the subject, we have the following concerns regarding Manpower allocation at Site:

  1. From 01 Feb,2017 to 09 Feb, 2017 our Manpower was 21 Carpenter+14 Masons+11 Helpers
  2. From 09 Feb,2017 to 19 Feb, 2017, our Manpower was 16 Carpenter+12 masons + 10 Helpers
  3. From Today, 20 Feb,2017, our Manpower is 12 Carpenter + 10 Masons + 10 Helpers.

As you can see, our manpower is decreasing everyday although our work activities are increasing :

Housekeeping, Blockwork, Internal Plastering for walls and ceiling, external plaster, ceramic work etc.

With this manpower we cannot reach 30% of our target.

This is for your intimation and necessary action.

Thanks and Regards,

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version