Issue for additional tile order

Tile

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Issue for additional tile order from M/s xxx and Al xxx,  as well as the new  tile nomination for tile code TL-01, TL-08, TL-09 from ID drawing

Dear Sir,

With reference to the above and our letter ref :CC/AP/295/17 DT.23.02.17,  we would like to inform you that, kindly finalize for the tile from M/s Envirotech and M/s Al shaya for additional area as per revised schedule and note the following:

  1. This additional tile work either client can supply the material from M/ s  Al shaya and M/s envirotech or we need engineer’s instruction to proceed to order for this addaitional scope i.e., variation which include the floor tile of the future cafetaia in basement .
  • The new ID drawing issued with the tile code TL-01, TL-08 & TL-09 , the selection to be made by the client, supplier to be nominated and tile to be supplied .

So, this is for your kind intimation and to do needful .

request you to please release the MEP IFC drawings for the 14th floor at the earliest.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan