Intimation for the partition wall variation for time and cost

Engineering Submittals

Engineering Submittals

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding intimation for the partition wall variation for time and cost

Dear Sir,

With reference to above and as per your letter ref no:AP/269/CC/224 dt.30.01.17 we are intimating for the variation for the time and cost and kindly note the following:

  1. We are attaching all the communication in summarized manner and the involvement of client within the communication protocol and outside discussion which is self-explanatory.

So we are not agree with your statement that “client have not instructed for higher STC value”.

              This is the ethical decision made by client representative (CR),  Contractor follow this with the effective manner  to support the project , since client representative has  decided infront of the consultant, contractor discussed  along with the supplier and  client representative need to honor his decision .

So, kindly review all the documents which are self-explanatory as the  issue started on dated 26.06.16 till 15 .01.17 as well as still many items are pending from the employer till date and contractor will not held responsible for any further delay and decision to be taken prior to execute the work from 3rd floor for cost and time.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager