Extension of Performance Bond Guarantee

Advance-Payment-Bank-Guarantee
Advance-Payment-Bank-Guarantee

Our Ref:  xxx

Date: xxx

To                           : xxx Contracting LLC

                                  P.O. Box xxx

  Dubai, U. A. E.

Attention            : Mr. xxx

Project                 : xxx at Jumeirah First, Dubai

Project                 : MH-0080 Port de la Mer Phase 1 (plot 2), Dubai

Subject                 : Extension of Performance Bond Guarantee

Dear Sir,

We are in receipt of your letter ref: xxx dated 15 September xxx and we would like to inform you that it is confirmed during the meeting held on 23 December xxx on site that since xxx has no pending DLP works, the Main Contractor does not require any further extension for our Performance Bond.

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.