Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E

Subject:           Regarding dry wall partition work delay issue and intimation for the rework of partition at second floor

Dear  Sir,

With due respect and subject mentioned for delay in your previous communications  (ref : AP/269/CC/256 dt 27.02.17,  & AP/269/CC/263 DT.06.03.17,  )we always expect  contractor’s proactive efforts be measured impartially without any influence and unbaised  manner ,please be consider the following inline for partion work issue and delay:

  1. Second floor partion wall closed without having any media hub drawing / material/ GRMS /home center drawing . So, we must remove the Gypsum sheet wherever  it required ,to fix the GI boxes for media hub and plywood  support for home center as well as GRMS requirement . So, it will be varaition in time and cost for second floor area.

Will contractor loss will be considered and judged by you?

So, this is for your kind information that,  the contractor continuing without having  clearance / nomination/material /drawing issue including financial losses of mock up as well as continuing the work at second floor . Still your blame of delaying in the partition may  justify? Or all the issues mentioned by the contractor are not valid?

 Please confirm all the rework variation will be approved and we need Engineer’s instruction to  continue the partition work without incorporationg the requirement of media hub , GRMS including final decision to clear the issue for third floor and  hereby contractor’s notifying that they will not responsible for the partition work and delay of the project.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager