Discrepancy in nomination letter issued

Variation notification
Variation notification

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject     :  Discrepancy in nomination letter issued on 15th August xx xxx and another communication xxx ON 19TH August xxx.

Dear Sir,

With reference to above, we have two different instructions which created confusion to us due to discrepancy in the instruction as explained below.

  1. The nomination issued 15th august AP/269/313 your nominated sub contractor is M/S Al Reman Building maintaince LLCand matirial White Granite & Brown Granite for sills.
  2. Your communication on 19th August 17 AP/269/CC/410 you confirmed the “White Tassos” for the window sill for the blue room and” Nano Whilte” (previously approved) for Orange room.
  3. Our describtion in item no 1 and 2 as described above have descrepency and we are unable to decide , shall we follow the 15th August 17 or 19th August 17.
  4. Kindly note that the sill size in width varring from 150mm to 350mm at various location /drawing /site condition but your nomination is issued for only 300mm which is not as per our drawing since sizes are varring order to be placed as per drawing size.

So, kindly review and advise for the decrepency btween two communication for same item from your office as well as the requirment of sill size also to be reviwed and revise nomination to be issuedif required.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version