Default on Progress Payment

Notice of Delay in Payments

Notice of Delay in Payments

Our Ref: xxx

Date: xxx

To                           : xxx Construction Engg. Corp. (Middle East) LLC

                                  P. O. Box xxx

  Dubai, U.A.E.

Attention            : Mr. xxx

Project                 : xxx – Zabeeel Second, Dubai, UAE.

Subject                 : Default on Progress Payment

Dear Mr. Chen,

We refer to our previous letters on the subject and xxx replies’

  1. Xxx letter No. xxx dated 5th of May xxxx
  2. CSCEC letter No. xxx dated 6th of May xxxx
  3. Xxx letter No. xxx dated 11th of May xxxx
  4. CSCEC letter No. xxx dated 12th of May xxxx
  5. Xxx letter No. xxx dated 19th of May xxxx
  6. CSCEC letter No. xxx dated 21st of May xxxx
  7. Xxx letter No. xxx dated 28th of May xxxx
  8. Xxx letter No. xxx dated 1st of July xxxx
  9. Xxx letter No. xxx dated 26th of July xxxx

We refer to our previous letters relating to your ongoing defaults on our progress payments.

Payment against IPA No.7

Payment against IPA No.8

Payment against IPA No.9

Payment against IPA No.10

Certification of IPA No.11

Short certification and detention charges

Delay in issuing NOC or original signed certificate

Your ongoing unilateral actions to differ and delay our payments has put Xxx in extreme financial stress since your actions are directly impacting our cash flow and our ability to maintain our supply chains. This is therefore limiting our ability to maintain healthy levels of production. xxx is held liable for that.

Accordingly, Xxx will not be liable for any delay caused by the above as such delays are on the account of xxx acts. In addition, we reserve our rights under the terms of our Subcontract Agreement for an Extension of Time (EOT) equivalent to the same number of days by which our progress payments are delayed.

In the same line, Xxx will not be held liable for any impact the above may have on the production or delivery of pods, or for any direct or indirect impact this may have on the site progress. The liability resides with xxx.

Xxx is no longer able to sustain such serious delays in payment as this has now restricted our ability to release associated payments to our transport suppliers. Accordingly, we now find ourselves in a position where we can no longer maintain transportation of completed pods to your project.

All rights are reserved

Yours faithfully,

On behalf of xxx  LLC

xxx

Project manager