Checklist For Above Ground Water Piping Installation
CHECK LIST FOR: INSTALLATION OF COLD AND HOT WATER PIPING SYSTEM AND ACCESSORIES Above Ground | Ref. No: Rev. No: 0 Page : 1 of 1 |
SUBCONTRACTOR | X | CONTRACTOR |
SECTION OF WORK: Water supply LOCATION: LEVEL: WIR No.: |
STAGE | ITEM | Checked by | Checked by | Date |
S/C | CONT | CONS. |
SETTING OUT | Check Layout | | | | |
MEP/CIVIL | Check Level. | | | | |
Chipping in the wall. | | | | |
INSTALLATION | Check for Services Clearances, and the same approved by consultant site team (civil) | | | | |
Check materials are as per approved material submittal. | | | | |
Check that size of pipe is as per approved drawing. | | | | |
Check that all pipes passing inside the wall installed as per approved shop drawings. | | | | |
Check the installed isolation valves are as per location shown in approved shop drawing | | | | |
Check that expansion / contraction joints are provided as per approved shop drawings. | | | | |
Check that Air vents installed as per approved shop drawings. (With Isolation valve). | | | | |
Check that water hammer arrestor is installed as per approved shop drawings. (With Isolation valve). | | | | |
Check PRV’s are installed as per approved shop drawings. | | | | |
Ensure that the Backflow preventers installed as power approved shop drawings. | | | | |
Check that pipes have been tested for leaks. (1.5 working pressure – 24 hours) | | | | |
Check that network is cleaned by Chlorine as per method statement point 7.9. | | | | |
Check that samples (from network/ and tank) are sent to ITL test (third party) to check water quality. | | | | |
Check that service identification labels are provided on exposed pipes and in access doors. | | | | |
Check that annular spaces between pipes and sleeves have been sealed with approved material. | | | | |
|
For S/C QA/QC: | Date: | FOR CONTRACTOR QA/QC: | Date: | For CONS. Rep.: | Date: |
Name: | Sign: | Name: | Sign: | Name: | Sign: |